Data-Centers-NC-v4 EAp2:Minimum energy performance

Waste heat recovery

I have a question concerning waste heat recovery in data centers. Recovery of the waste heat (directly or assisted with heat pumps) is part of many guidelines and best practices concerning data center design and operation but can you take benefit of it in LEED Energy Performance credits?

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Mon, 10/05/2015 - 21:48

Probably. You will need to make the case that it is not standard practice in your area. See also the spreadsheet available to calculate data center energy savings. Not sure if that is one of the strategies included or not. http://www.usgbc.org/resources/minimum-energy-performance-data-center-calculator

Fri, 07/03/2020 - 19:42

Hi Paula, was your approach accepted by reviewers?