I have a homeless shelter project. It contains office and residences in it which do not have any transients. However, the project also serves as a church one day a week where approximately 326 people come on Sunday (and only Sunday). I assumed that my Peak Transient and Daily Average Transient would be identical: 326. My review cam back saying that this may have been calculated incorrectly.

I believe this is calculated correctly, but I was hoping to hear a comment or two about any experiences with this. Do you believe this is accurate?