Hello, we are locating our recycling area at the underground parking lot. because of the layout is tight we are planning to use the height (almost 20 ft) of the floor to build a mezanine and maximize our sf. Would this solution comply with the pre requisite?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
December 20, 2013 - 6:02 pm
Citlati, I don't see any issue, as long as the recycling area is sufficient, and accessible.