I have a 4 floor building in china, it’s a manufacturing facility. In short, they will construct the entire building (core and shell) but will not do the interior of floors 3 and 4 until “they feel the time is right”, they said 2-5 years. My problem is they are steadfast on obtaining New Construction certification. Is this possible? Or do you need full build out of building? How would I calculate FTE or do commissioning? Has anyone run into this problem before? many thanks!
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
September 5, 2012 - 10:37 pm
Shawn, you can do this, but it will be a little complicated at times.Please enter questions on specific credits in those forums.