I have a 4 floor building in china, it’s a manufacturing facility. In short, they will construct the entire building (core and shell) but will not do the interior of floors 3 and 4 until “they feel the time is right”, they said 2-5 years. My problem is they are steadfast on obtaining New Construction certification. Is this possible? Or do you need full build out of building? How would I calculate FTE or do commissioning? Has anyone run into this problem before? many thanks!

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Thu, 09/06/2012 - 02:37

Shawn, you can do this, but it will be a little complicated at times.Please enter questions on specific credits in those forums.