Dear all,
we are making Core Shell project. Is it necessary to take into consideration flush out procedure during preparation of IAQ management plan in scheduling point?
If so, what are the relevant requirements?
Does contractor need to replace all filtration media just before occupancy when HVAC is not planned to be used during construction?
Any comments/suggestions will be appreciated.
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11477 thumbs up
November 20, 2011 - 10:30 pm
BH, a flush-out is not part of this credit for CS projects.If HVAC is not used during construction, then there is not a requirement to replace filters.