To clarify, we do have the proper pressurization to prevent smoke from entering our building. It is just a matter of how do we measure, since the reference guide stipulates the doors must be closed. It assumes there are doors to close.

Fri, 01/21/2011 - 15:07

I don't think there is a protocol for this, no. I think you would need to come up with something on your own (with technical support) that seems as rigorous as possible, and propose it to GBCI. Since this is a prerequisite, a CIR might be a worthwhile investment.