Medical gas system - part of fundamental commissioning?

NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Veronika Sundberg  on 

Hello, my qeustion is regarding our medical gas system and if it should be part of the fundamental commissionig for LEED? We will undertake commissioning of the system but would prefer to excluded

3
Default Avatar
Environmental Engineer - Certification
Skanska Sverige AB
LEEDuser Basic Member
94 thumbs up
Mon Oct 13, 2014, 3:27 pm

Do we need to Commission these systems?

NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Maya Karkour  on 

Dear Sirs, I just want to double check if we need to commission, as part of the LEED PRerequisite / Credit, the following systems: 1) Pumps for water distribution, irrigation, sewage, and fuel 2)

3
Default Avatar
EcoConsulting
LEEDuser Basic Member
549 thumbs up
Mon Oct 13, 2014, 12:56 pm

INSULATION ON SHELTERED WALLS

CS-2009 EAp2:Minimum Energy Performance
posted by  Ana Paula Quiros  on 

We are assessing a C&S 2009 project. We have two sheltered walls with neighbors on both sides. The walls from the neighbors are not along all the project walls.

3
Architect, LEED AP BD+C
Livet Consulting
LEEDuser Basic Member
0 thumbs up
Fri Oct 10, 2014, 9:45 pm

Can you add a new credit while in the Construction Review Phase?

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by  Mike Stopka  on 

I am working on a project that is currently in the Construction Preliminary Review Phase. We are realizing that Gold Certification is a reality now.

4
Energy Program Specialist
PA DMVA
LEEDuser Expert
626 thumbs up
Fri Oct 10, 2014, 8:36 pm

kitchen hoods

NC-2009 EAp2:Minimum Energy Performance
posted by  HOUCINE TLEMSANI  on 

Hi, I am working on a dining facility where we have two makeup air units serving the kitchen hoods.

6
Default Avatar
Mechanical Designer
MEP Engineering Solutions, Inc
LEEDuser Basic Member
8 thumbs up
Fri Oct 10, 2014, 7:54 pm

Survey for Sixth Graders

Schools-2009 IEQc7.2:Thermal Comfort—Verification
posted by  Matthew Heaton  on 

A comment that came back on our IEQc7.2 design review asked us to "Please provide confirmation that the survey will be administered to include all building occupants, including students of grades s

2
Sustainable Building Consultant
Green Bridge Consulting
LEEDuser Expert
28 thumbs up
Fri Oct 10, 2014, 3:45 pm

Exterior lighting power

NC-2009 EAp2:Minimum Energy Performance
posted by  VICTOR MORENO  on 

Hello. One review comments that i have received about E&Ap2 prerequisite is: 2. No exterior lighting power has been modeled for the Baseline or Proposed Case.

4
Green Building Energy Consultant
Green Living Projects
LEEDuser Basic Member
2 thumbs up
Thu Oct 9, 2014, 11:37 pm

Lose Leed Certification?

General forums
posted by  Tim Meadows  on 

We have a parking deck that is LEED certified. We have several EV charging stations in employee and visitor areas.

2
Founder & CEO, LEED Fellow, BREEAM Fellow
BuildingWise LLC
LEEDuser Expert
224 thumbs up
Thu Oct 9, 2014, 7:12 pm

Reinforcement Steel in concrete

NC-2009 MRc4:Recycled Content
posted by  Lise Dannesboe  on 

Hi! How is reinforcement steel calculated in an assembly of reinforced concrete.

4
LEED-AP BD+C
GREENSQUARE
LEEDuser Expert
261 thumbs up
Thu Oct 9, 2014, 2:36 pm

Site

NC-2009 PIf1:Minimum Program Requirements
posted by  K Nakamura  on 

We have a project- scope is 2 new buildings, no sitework/landscape.