Buildings Attached to non LEED-certified buildings

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  Zachary Mathern  on 

I am referring to the Supplemental Guidance to the MPR's; All Attached Buildings, 2) Treating Energy Systems.

1
Fri Jul 12, 2013, 6:08 pm

Uploaded drawings

NC-2009 PIf4:Schedule and Overview Documents
posted by  Michael Beattie  on 

I've been waiting to upload the drawings for our project until the revisions generated by Owner and Contractor have been complete, and the drawings reflect what's actually being constructed.

1
Fri Oct 18, 2013, 8:17 pm

Surface Water Management Credits

LEED for Homes (LEED-H) Forum
posted by  Eva Pong  on 

(Credit 4.1 states: 'Design the lot such that at least 70% of the buildable land; not including area under roof, is permeable or designed to capture water runoff for infiltration on site.' ) Is the

0

School as a Teaching Tool vs ID Green Building Education Program

Schools-2009 IDc3:The School as a Teaching Tool
posted by  Rebecca Molldrem  on 

Since ID Credit 3 is an option under LEED for Schools, does this mean that if a project is not pursuing this, they also wouldn't be able to pursue an Innovation in Design credit for a Green Buildin

1
Thu Sep 5, 2013, 11:47 pm

Calculating parking area

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  Sean Hogan  on 

I have a project seeking certification which has approximately 750 surface car parking spaces.

1
Fri Jul 12, 2013, 6:06 pm

Complete information on Variable Speed Control

CI-2009 EAc1.3:Optimize Energy Performance—HVAC
posted by  Mike D  on 

There are no pumps or VAV fans on this project which are 5hp or greater.

1
Thu Jun 27, 2013, 12:01 am

Energy modeling review question

NC-2009 EAp2:Minimum Energy Performance
posted by  Santiago Rodriguez  on 

For a LEED project that recently received the preliminary design review comments, we were asked to analyze and correct the documentation to comply with pre-requisite EAp2.

1
Wed Jun 26, 2013, 11:20 pm

Process Equipment Refrigerant

EBOM-2009 EAp3:Fundamental Refrigerant Management
posted by  Jalal Avades  on 

I have a school building with an old walk-in coolers/freezers used in the Kitchen. Those do have CFC refrigerant.

1
Tue Oct 15, 2013, 11:24 am

Group project certification and PIf2

LEED Guidance for Campuses and Multiple Buildings
posted by  Noriko Nagazumi  on 

The following message appears if a total of more than one building is selected in "Number of buildings attempting certification as part of this LEED Application:" at PIf2: "At present, only one bui

1
Thu Jun 27, 2013, 11:43 am

Plant space in Default occupancy

NC-2009 PIf3:Occupant and Usage Data
posted by  Mike D  on 

We have included all areas of the building within the Default Occupancy Table. However, there is still the Plant Space we have not included. Can this be omitted?

1
Thu Jul 25, 2013, 6:28 pm