Topic | Recent |
---|---|
Green WallCS-2009 EAp2: Minimum Energy Performanceposted by Yoyo Shek on Mar 12, 2013, 11:51 pm
Does anyone have idea if we could model the benefit of using green wall (Vegetated)? Last reply: Yoyo Shek, Mar 19, 2013, 12:06 am |
|
Future-Fit Out Spaces LEED Certified or NotNC-2009 PIf1: Minimum Program Requirementsposted by Catherine Blakemore on Mar 22, 2013, 3:41 pm
My inquiry is in reference to... Last reply: Catherine Blakemore, May 1, 2013, 7:52 pm |
|
LEED Interpretation Rulings-When can they be followed?NC-2009 IEQc4.4: Low-emitting materials - composite wood and agrifiber productsposted by Judy Landwehr on Apr 1, 2013, 6:16 pm
Which of the below statements applies to a... Last reply: Tristan Roberts, Apr 22, 2013, 4:00 pm |
|
Green Data CenterNC-2009 EAc1: Optimize Energy Performanceposted by Jatuwat Varodompun on Apr 10, 2013, 1:23 pm
Does anyone know about the modeling baseline of the a data center. Can we use 90.1 or do we have to use something else? Last reply: Mara Baum, May 30, 2013, 12:26 pm |
|
Can an Off-site parking garage be used to achieve credit?NC-2009 SSc7.1: Heat island effect - nonroofposted by Breffni O'Rourke on Apr 23, 2013, 6:37 pm
We are examining a project that will include a multi-story parking garage that will not be within the LEED boundary. The garage will be constructed (likely concurrently) to serve the certified... Last reply: Erin Holdenried, May 1, 2013, 6:17 pm |
|
Modular constructionNC-2009 MRc2: Construction Waste Managementposted by Courtney Royal on May 3, 2013, 1:44 pm
Our projects entire building will be built as modular construction and assembled off-site in Brooklyn and when completed will be transferred to Manhattan. How does this work for the credit?... Last reply: RETIRED, Nov 7, 2017, 1:33 pm |
|
DES Energy CostNC-2009 EAc1: Optimize Energy Performanceposted by Marina Andrade on May 13, 2013, 3:13 pm
According to the Advance Energy Modeling for LEED, page 49 option 1, I should model all upstream equipment as cost neutral. However on the LEED guidelines for district energy systems says that we... Last reply: Marina Andrade, May 28, 2013, 10:05 am |
|
Performance Period starts after constructionPerformance Periodposted by Karin Wohlert on May 13, 2013, 7:21 pm
Our project team is building an addition to an existing facility. The owner would like to certify the whole building. The existing building was certified LEED... Last reply: Karin Wohlert, May 23, 2013, 6:05 pm |
|
Regarding LEED certification for District Cooling PlantGeneral forumsposted by Ramesh Narayanan on May 21, 2013, 9:28 am
Hi Last reply: Marcus Sheffer, May 22, 2013, 9:07 am |
|
Exterior Envelope CommissioningNC-2009 IDc1: Innovation in Designposted by Eric Thompson on May 22, 2013, 10:12 amMacken. http://www.leeduser.com/blogs/leed-v4-public-comment-forum-leed-takes-ne... They heard me, considered it, and did not agree. Please do not take any of this wrong, as I am a huge promoter of ECx... Last reply: Scott Bowman, May 22, 2013, 4:56 pm |