Post a question or comment
Filter by location
Forum
Topic
Replies
Recent

Modeling Toilet exhaust fans

NC-2009 EAp2:Minimum Energy Performance
posted by  Matt Scott  on 

Let's say you have a proposed zone being conditioned by an RTU with only a supply fan and you also have a small exhaust fan exhausting air directly from a toilet room, and that's the extent of your

3
Default Avatar
Engineer
N.E. Fisher & Associates, Inc.
LEEDuser Basic Member
12 thumbs up
Tue Mar 14, 2023, 8:49 am

Plug loads for server rooms

NC-2009 EAp2:Minimum Energy Performance
posted by  MARCIO OROFINO  on 

Hi. I am working for this project - a small one-floor office building, which has a 14 m2 server room.

5
Tue Mar 14, 2023, 8:39 am

Documentation for No Cooling Tower

Pilot-Credits WEpc94:No Cooling Tower
posted by  Marelle Davey  on 

Hi everyone,

Just wondering what documentation have folks used to achieve this credit? Is any documentation required besides mechanical drawings? 

Thanks!

2
Sustainability Consultant
WSP
LEEDuser Expert
0 thumbs up
Tue Mar 14, 2023, 8:20 am
1
Tue Mar 14, 2023, 11:56 am

Warehouse ventilation filtration system

Warehouses-NC-v4 EQp1:Minimum indoor air quality performance
posted by  Gabriela Mena   on 

I am working on a warehouse project that has supply fans (wall mounted) to ventilate the space, we are pursuing the Enhanced IAQ credit <<Interior Cross Contamination Prevention>>, this

4
Practice Leader - Sustainability
EUA
LEEDuser Expert
510 thumbs up
Sun Mar 12, 2023, 4:12 am

Integrative Process Facilitator

LEED v4.1 Discussion Forum
posted by  Edward Reifenstein  on 

The Integrative Process credit for v4.1 BD+C: New Construction refers to an "Integrative Process Facilitator" who has responsibility for running the early charrette and tracking the results, u

2
CEO
Green Commons, LLC
LEEDuser Expert
586 thumbs up
Sun Mar 12, 2023, 3:53 am

Food Service Equipment

CI-v4 EAc5:Enhanced refrigerant management
posted by  ESD Engineer  on 

For a LEEDv4 CI project, does food service equipment such as ice cube machines, ice machines, and chiller freezers need to be documented?

3
Default Avatar
Associate Director
M Moser Sustainabililty
LEEDuser Premium Member
0 thumbs up
Sun Mar 12, 2023, 3:50 am

LEED O+M Campus Chiller Plant

EBOM-v4.1 EAp3:Energy Performance
posted by  Rajarajan Sekar  on 

We are trying to go for LEED O+M  certification in one  of our buildings which has a Chiller plant in it along with other occupied places

0