Materials ConsideredCS-2009 IEQc4.2: Low-emitting materials - paints and coatingsposted by Angela Saggin on Jun 4, 2012, 4:49 pm
Hi! I've just started studying this credit and me and my colleagues were arguing about what materials exactly we should consider to achieve this credit. "Requirements" says that we... Last reply: Emily Catacchio, Jul 13, 2012, 6:51 pm |
|
Materials ConsideredNC-2009 IEQc4.2: Low-emitting materials - paints and coatingsposted by Angela Saggin on Jun 4, 2012, 4:50 pm
Hi! I've just started studying this credit and me and my colleagues were arguing about what materials exactly we should consider to achieve this credit. "Requirements" says that we... Last reply: Angela Saggin, Jun 5, 2012, 3:07 pm |
|
ESC PLAN LanguageCS-2009 SSp1: Construction Activity Pollution Preventionposted by Esteban Undurraga on Jun 6, 2012, 12:12 pm
Dear all, I think this question will be useful for people doing LEED outside the US.. Last reply: Ron Dean, Jul 11, 2012, 6:53 pm |
|
Performance period timingEBOM-2009 MRc9: Solid waste management - facility alterations and additionsposted by Kim Wajda on Jun 7, 2012, 11:32 am
If performance periods for different credits have to end within the same 30 day period, and our solid waste was hauled and tracked during the period of the project's additions and alterations,... Last reply: Jessica Hawley, Apr 8, 2015, 10:58 am |
|
Water Guidance Rationale for "Both-Outside Fixtures Included"CI-2009 WEp1: Water Use Reductionposted by Michelle Rosenberger on Jun 7, 2012, 6:45 pm
If you have fixtures both within and outside your space to serve tenants and you are pursuing WEcr1, what is the documentation rationale for not including the "outside" fixtures in WEpr1 and then... Last reply: Michelle Rosenberger, Sep 6, 2012, 1:12 pm |
|
3 types of glass in the proposed designNC-2009 EAp2: Minimum Energy Performanceposted by Tarek Dalati on Jun 8, 2012, 8:20 am
In the building we are modeling 3 tyes pf glass (3 different U values and SC) are used by the architect.Is it acceptable for EAP2 that I do the following: Last reply: Marcus Sheffer, Jun 8, 2012, 11:42 am |
|
Heat Recovery wheelNC-2009 EAp2: Minimum Energy Performanceposted by Tarek Dalati on Jun 9, 2012, 1:18 am9:54 am The best place to post software specific questions is the eQUEST discussion forum found on onebuilding.org There is extensive discussion in the archive on this subject. First question-... Last reply: Marcus Sheffer, Jun 11, 2012, 10:13 am |
|
baseline HVAC system for Energy modellingNC-2009 EAc1: Optimize Energy Performanceposted by Grace Ming on Jun 11, 2012, 8:00 am
Hello All, We are now preparing the Energy modelling for one of our projects located outside USA. It is a 2 storey non-residential building with VRV system for cooling only. We... Last reply: Marcus Sheffer, Jun 13, 2012, 10:05 am |
|
design phase review appealLEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Todd LaFreniere on Jun 11, 2012, 5:50 pm
Our project is currently at the Construction Final Review Stage and we would like to submit an appeal on 2 of our Design credits. How is this done? I tried during the Construction Preliminary... Last reply: Bernard Sagaiyaraj, Mar 12, 2013, 10:30 pm |
|
Process Load for CSCS-2009 EAp2: Minimum Energy Performanceposted by Yu Wang on Jun 13, 2012, 7:39 am
Hallo everyone, Last reply: Marcus Sheffer, Jun 15, 2012, 9:18 am |