Lighting Controls in Jewelry StoreRetail-CI-v2009 EAc1.2: Optimize energy performance - lighting controlsposted by Luke Wild on Oct 2, 2014, 11:42 am
We are working on a LEED project for a jewelry store which has millwork with lighting in it all around the store. Would the connected lighting load for the occupancy sensors and daylight sensors... |
|
Golf Course Clubhouse Project AdviceEBOM-2009 EAc1: Optimize Energy Efficiency Performanceposted by Johanna Hendricks on Oct 9, 2014, 12:40 pm
Hello, We have a client that has approached us about the possibility of certifying a golf course clubhouse via LEED... |
|
Limited LEED CI boundaryCI-2009 MPR2: Must be a complete, permanent building or spaceposted by Kevin Wilcox on Oct 9, 2014, 4:47 pm
We have a project where the scope of interior alteration is limited to multiple core restrooms (multiple floors) to incorporate ultra low flow fixtures, minor remodel for compliance with building... |
|
Pilot credit # 45Pilot-Credits SSpc45: Site assessmentposted by Devani PERERA on Oct 9, 2014, 9:55 pm
I do agree with Loic that in France, projects that pursue the french certification HQE would perform a site analysis to assess the needs, opportunities and issues that need the most attention. I... |
|
Long Term Service ContractNC-2009 EAc4: Enhanced Refrigerant Managementposted by Erin Holdenried on Oct 13, 2014, 1:40 pm
Does anybody have an example of a long term service contract, or know specifically what needs to be included in the contract in order for it to be accepted by the... |
|
Pilot vs v4 Demand Response- Full AutomationPilot-Credits EApc8: Demand responseposted by Jennifer Wehling on Oct 13, 2014, 3:25 pm
I have a LEED NC 2009 project that wants to use... |
|
Vista Users Out of LuckLiving with LEED Online - quirks, bugs and hiccupsposted by Cynthia Kaplan on Oct 15, 2014, 4:22 pm
On 9/26/14 I lost the ability to view credit tempolate forms in LOL v3. Three weeks and 163 phone minutes later, the final verdict from... |
|
LEED Site boundary – underground parkingHealthcare-v2009 MPR3: Must use a reasonable site boundaryposted by Florian Schmidtchen on Oct 17, 2014, 8:18 am
Hello all, We are working on a project with 2 stories for underground parking. About the half of the parking space is built for building users as required by local zoning requirements. The... |
|
Ventilation EffectivenessGeneral forumsposted by Dustin Balton on Oct 20, 2014, 10:26 am
I am working for a client who has a variable refrigerant HVAC system with a separate fully condition ventilator supplying fresh air. They are over budget and the contractor is proposing ducting... |
|
Summary marked "N"NC-2009 PIf3: Occupant and Usage Dataposted by Ryan Kurlbaum on Oct 20, 2014, 11:54 am
We have completed this form and for some reason continue to have the "summary" box marked as "N". We do not have additional details to add - any ideas on what could be missing for us to complete... |