Forum quick links
Data Center Baseline HVAC System
NC-v4 EAp2:Minimum energy performanceposted by Vassil Vassilev on
Hi Markus, Thanks for your reply. I've been trying to undestand the explanation of 90.1-2013 User's Manual, page G-35.
Rainwater from roof
NC-2009 SSc6.2:Stormwater Design—Quality Controlposted by Viktor Reutherborg on
Hi, Question one. We are in a semi-arid watershed. In the calculations, we count on 0,75 inch rainfall during 24 hours? We are planning to clean the rainwater from the roof.
DATA Center
NC-v4 EAp2:Minimum energy performanceposted by Vassil Vassilev on
Markus, thanks again. Since the English is not my mother tonge, sometimes I'm geting confused by enterpreting some explanation although I'm already 37 years in the HVAC branch.
Updated documentation and resubmittal in construction phase
posted by Emmanuel Pauwels on
Our project is going to submit for Construction Review for a BD+C project. We applied a split review. Design Credits are approved. During Construction some room dimensions changed.
New Review Comment
CI-2009 IEQc7.1:Thermal Comfort—Designposted by Aaron Luthien on
Usually we have fulfilled this credit by using pyschometric charts provided by Climate Consultant software. I documented temperature and humidity ratios together with metabolic rates.
Regional Priority on this credit
CI-2009 SSc1:Site Selectionposted by Katie Peterschmidt on
Hello - I'm doing a tenant guideline for our C&S project and want to make sure I'm leading the tenants properly in what they can automatically achieve.
Engineered ventilation system - operable windows
NC-2009 IEQp1:Minimum IAQ Performanceposted by Ritwik Kakati on
In our high-rise multifamily building project, we are trying to demonstrate IEQp1 compliance for living rooms & bedrooms by showing an engineered ventilation system whereby toilet exhaust fans
Landscaping - MRc4
NC-2009 MRc4:Recycled Contentposted by frederick muscatello on
Can landscape and irrigation materials be included?
Regarding LEED Project Boundary
EBOM-2009 MPR3:Must use a reasonable site boundaryposted by Shelendra Kumar on
Hello Team, One of our project which is already LEED NC certified and now wants to go for EB certification, our concern is about its project boundary. earlier certain boundary has defined for NC
Functional Performance Testing
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Giulia Faccio on
Our project, registered under LEED 2009 Italia NC, consists in a building whose occupancy will take place in October 2014.