VOC Testing - ISO EU Standard

NC-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatings
posted by  Nowfal Kunju Muhammed  on 

If VOC content is mentioned as per ISO EU standard, is it acceptable for LEED?

1
Sun Aug 31, 2014, 3:03 pm

Ashrae 90.1.2010, HVAC Table 6.8.1.C Water Chiling Packages Eff.

NC-2009 EAc1:Optimize Energy Performance
posted by  ABHIJIT PISAL  on 

In the table there is a mention of Path-A and Path-B. Pl. help as to how to interpret Path-A and Path-B.

1
Tue Sep 2, 2014, 12:53 pm

Urban agriculture in high density, zero lot line project.

NC-2009 SSc5.1:Site Development—Protect or Restore Habitat
posted by  Nadia Ayala  on 

Hi everyone, I have a project in Mexico where we are trying to create a rooftop food garden.

1
Mon Dec 8, 2014, 6:27 pm

LEED AP - Experience required

General forums
posted by  Rita Barata  on 

Is the Estidama experience valid as LEED experience for the LEED AP exam?

0

Documentation if the building structure remains the same

CS-2009 MRc1:Building Reuse—Maintain Existing Walls, Floors and Roof
posted by  Nicole Isk  on 

We have a Major Renovation project where NO changes on the building structure will occur.

1
Thu Oct 9, 2014, 8:46 pm

Data center - Baseline HVAC System

NC-v4 EAp2:Minimum energy performance
posted by  Vassil Vassilev  on 

Hi Markus and all coleagues, In the Data center I'm about to start modeling, there are 4 IP rooms. Each of these rooms has IP load with a power density of 3.2 kW/m2 or 297 W/ft2.

1
Tue Sep 2, 2014, 1:18 pm

Flushing toilets with drilled corrosive non potable water

NC-2009 WEc3:Water Use Reduction
posted by  Viktor Reutherborg  on 

We have an adjacent property (with the same owner) that has to remove non potable water from its foundation. This groundwater flows in a large part from our property.

0

Engineered ventilation rates

NC-2009 IEQp1:Minimum IAQ Performance
posted by  LEEDme Lorenzi  on 

We are working on a office building in which there is an openspace. The outside openings largely cover 4% of the total floor area.

0

Data Center Baseline HVAC System

NC-v4 EAp2:Minimum energy performance
posted by  Vassil Vassilev  on 

Hi Markus, Thanks for your reply. I've been trying to undestand the explanation of 90.1-2013 User's Manual, page G-35.

1
Tue Sep 2, 2014, 2:22 pm

Rainwater from roof

NC-2009 SSc6.2:Stormwater Design—Quality Control
posted by  Viktor Reutherborg  on 

Hi, Question one. We are in a semi-arid watershed. In the calculations, we count on 0,75 inch rainfall during 24 hours? We are planning to clean the rainwater from the roof.

1
Tue Sep 2, 2014, 3:08 pm