Topic | Recent |
---|---|
Does a Data Hall should be modeled with an Air Economizer in BaselineNC-v4 EAp2: Minimum Energy Performanceposted by Rajat Wadhwa on Jan 30, 2025, 3:33 pm
Hi, I am working on a Data Center Project in Chicago and the... Last reply: Shashank Singh, Jan 31, 2025, 1:17 am |
|
Project Occupancy when we are only complying with Indoor Water Use Reduction prerequisite under prescriptive path?CI-v4 WEp1: Indoor water use reductionposted by Edgar Arevalo on Oct 25, 2024, 3:17 pm
So we have an interior fit out project where we can only comply with the Indoor Water Use Reduction prerequisite and not the credit. Since we are only complying with the prerequisite via... Last reply: emily reese moody, Jan 30, 2025, 10:20 pm |
|
Pilot Credit MRpc131: Circular ProductsNC-v4 INc1: Innovationposted by Amber Morris on Jan 6, 2021, 11:39 am
Hello all, Our project team is currently pursuing this credit and was able to achieve it through door hardware manufacturers such as Sargent, McKinney, Norton, Pemko and CECO since they... Last reply: Amy Danner, Jan 30, 2025, 5:06 pm |
|
Unregulated loads in production plantNC-v4 EAc2: Optimize Energy Performanceposted by Julio Fernandez Amodia on Jan 20, 2025, 1:15 pm
Hi to all, Last reply: Julio Fernandez Amodia, Jan 30, 2025, 6:13 am |
|
IN- Heat Island Mitigation with Cool WallsNC-v4.1 INc1: Innovationposted by Jorge Ramírez Hernández on Mar 14, 2024, 3:04 pm
Greetings, Currently I’m working on a building extension pursuing a LEED BD+C New Construction, the IN- Heat Island Mitigation with Cool Walls credit is being attempted, although some... Last reply: Ricardo Alarcon, Jan 29, 2025, 5:40 pm |
|
Baseline Building Information not availiableNC-v4 EAp2: Minimum Energy Performanceposted by Rajat Wadhwa on Jan 22, 2025, 5:40 pm
Hi, I am working on LEED ID+C project in which we do not have any info regarding COP of chiller, Fan Flow, Fan power, Pump power etc. So what should I do to input that? Should I use the same... Last reply: Marcus Sheffer, Jan 27, 2025, 5:22 pm |
|
Ownership of Attributes: On-Site PV with Utility ProgramNC-v4.1 EAc5: Renewable energyposted by Summer Minchew on Dec 15, 2023, 9:26 am
The LEEDonline form for this credit requires us to, "Upload On-site Renewable Energy Systems...Contract and evidence of renewable attribute ownership.
Last reply: Marcus Sheffer, Jan 27, 2025, 5:15 pm |
|
Appliance and Process WaterNC-v4 WEc2: Indoor water use reductionposted by Ricardo Sá on Nov 13, 2020, 5:17 am
De, we’re currently involved in a project of a new hospitality building in Europe that is pursuing LEED certification. In what relates with Indoor Water Use Reduction credit, since... Last reply: BuyAED India, Jan 27, 2025, 5:41 am |
|
ACP and InnovationPilot-Credits EApc143: Zero Energy Performance Index (zEPI) ACPposted by Mark Terpstra on Jan 21, 2025, 4:31 pm
The zEPI ACP is an pilot credit that can be used in place of the Optimize Energy Performance credit. It also appears in the innovation drop-down. Does using this ACP qualify as an... Last reply: Colleen Loader, Jan 24, 2025, 10:20 pm |
|
AQUASTAT's monthly rainfall and ETo rate: Historic vs AgERA5 Average yearPilot-Credits WEpc115: Whole Project Water Use Reductionposted by Jorge Ramírez Hernández on Jan 24, 2025, 4:11 pm
Hello, We are currently documenting the water efficiency alternative compliance path “Whole Project Water Use Reduction” for an industrial building. When... |