Forum quick links
LEED HC WE p1 - Process water use terminology
Healthcare-v2009 WEp1:Water use reductionposted by Sasha Peters on
Can someone please tell what is the meaning of "ADO" as mentioned in the LEED HC template WE p1 - Process water use reduction? It seems to be a value affecting total water use. Thanks.
Multi Layered App-Shop Primer-Primer-Topcoat VOC Numbers
NC-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatingsposted by Nilufer Senses on
We have multi-layered, anti-corrosive coating application for the steel structural elements in the interior. Layering is like this: Shop Primer, Primer and Top Coat.
Process Energy
CI-2009 EAp2:Minimum Energy Performanceposted by Graham Langton on
All, How does LEED CI and section 11 modelling view process energy? For an industrial / manufacturing facility with new process equipment in particular. In 90.1, process energy is not dealt with.
Clarification for LEED CI
NC-2009 MPR2:Must be a complete, permanent building or spaceposted by Rebekah Burke on
If we are doing a tentant improvement for the entire interior of a building, is it eligible to be certified under LEED-CI.
Returned product recycling
EBOM-2009 MRc7:Solid Waste Management—Ongoing Consumablesposted by Andy Plogsted on
The project that I'm working on contains a warehouse for shipping sold products. At times, metal products are returned because they are damaged or defective.
Daylight and Views - Simulation Documentation
NC-2009 IEQc8.1:Daylight and Views—Daylightposted by Candice Rogers on
Hello - This is my first time using the Simulation option for documenting Daylighting. For the Supplemental Daylight and Views Calculation Worksheet, do we represent our 5 ft.
punch list for air testing option?
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Carrie Laurendine on
the LEED reference manual states that punch list must be completed prior to flush out. However, it doesn't state either way if punch list must be completed prior to air testing.
FSC Registration
NC-2009 MRc7:Certified Woodposted by Ronnie Oleary on
ADVICE-01-010 FSC Online Claims Platform (OCP) Criteria Has anybody seen this? It looks to me like it is just getting certificate holders registered, which seems pretty easy.
Water Reporting via approved methods
NC-2009 MPR6:Must commit to sharing whole-building energy and water usage dataposted by Sara Goenner Curlee on
As I look through the two options to report energy and water usage, I'm a little unclear how one exactly reports the water consumption of a building.
Superstructure vs. Multiple Buildings Mid-Review Clarification
NC-2009 MPR2:Must be a complete, permanent building or spaceposted by Matthew Macko on
I am currently working on a large, outdoor retail shopping mall that includes multiple buildings, however we want to claim these buildings are more like connected ‘structures’ and therefore the who