posted by  Sara Zoumbaris  on 

Our project is shy of the second weekend trip threshold (108) by 1-ride. We are within walking distance of Amtrak, which has regularly scheduled pickups at our location twice a day.

5
Tue Jan 16, 2018, 6:37 pm

What transit type is the Subway (underground) System?

CI-v4 LTc3:Access to quality transit
posted by  Olga Yuil  on 

What transit type is the Subway (underground) System?

Is it light rail, heavy rail or commuter rail?

6
Sustainability Director, Certifications & Compliance
Jacobs
LEEDuser Expert
469 thumbs up
Tue Jan 16, 2018, 6:35 pm

Existing building curtainwall reduced glazing %

NC-v4 EAp2:Minimum energy performance
posted by  Wade Cooper  on 

I have an existing envelope that is a complete curtain wall assembly that is to be replaced.  The overall WWR for the building is over 70% currently and is being removed and redesigned to

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue Jan 16, 2018, 4:06 pm

Option 1: which software shall we use??

NC-v4 EQc7:Daylight
posted by  Ricardo Sá  on 

Hi,

 

we're experiencing lots of difficulties to correctly assess this credit. Some notes:

5
Energy Program Specialist
PA DMVA
LEEDuser Expert
626 thumbs up
Tue Jan 16, 2018, 3:48 pm

% of Herbs required

Pilot-Credits SSpc82:Local food production
posted by  Francesco Passerini  on 

Hello, we want to pursue this credit, but we have a doubt. Under all project description says "Herbs used for food preparation shall not exceed 25% of the area requirement.

1
Mon Jan 15, 2018, 3:35 pm

Gross area v. net area in PI Form 3 and IEQ8.1

NC-2009 PIf3:Occupant and Usage Data
posted by  James Bell  on 

PI Form 3 requires gross area of Occupied Space.

5
Managing Partner
Ecoimpact Consulting
LEEDuser Expert
171 thumbs up
Mon Jan 15, 2018, 10:20 am

Owner Provided Signage

NC-2009 SSc7.1:Heat Island Effect—Non-Roof
posted by  Summer Minchew  on 

I have a project that will have owner provided signage (naming signage) mounted to architectural canopies.

0

Roof Mounted Ventilation Intakes

Green Commons
posted by  Tate Walker  on 

Is anyone aware of research or guidance that has looked at VOC’s from roofing products and ventilation intakes?

2
Principal, Sustainable Design Director
SWBR
LEEDuser Premium Member
0 thumbs up
Fri Jan 12, 2018, 5:23 pm

Developer Incentives

Green Commons
posted by  Mona Lemoine  on 

Hello Green Gurus,

7
Associate | Senior Sustainability Consultant
DIALOG
LEEDuser Premium Member
0 thumbs up
Fri Jan 12, 2018, 4:57 pm

Fan - interior ventilation EFLH

NC-v4 EAp2:Minimum energy performance
posted by  Michael   on 

Hi,

i'm dealing with EFLH for interior ventilation in baseline and propose, over 8000h/year, double than another ones such us space cooling and receptacle EFLH, <4000h/year?

3
Default Avatar
Project Manager
LEEDuser Basic Member
14 thumbs up
Fri Jan 12, 2018, 2:34 pm