Ill advised to submit EAp2 and EAc6 under combined review?
NC-2009 EAc6:Green powerposted by Kathryn West on
If I submit for combined review and get comments on my energy model then my EAc6 REC purchase can't be approved, right?
Low-temperature chemical dishwashers
CI-2009 EAc1.4:Optimize Energy Performance—Equipment and Appliancesposted by Susan Di Giulio on
The kitchen consultant on our project has specified a Hobart LT-1 LOW-TEMP CHEMICAL DISHWASHER. While most Hobart products are E-Star, this one is not.
Modeling Water-source Variable Refrigerant Volume Systems
NC-2009 EAp2:Minimum Energy Performanceposted by Eric Webber on
Hey everyone, I have a question about the best software choice and modeling strategy for water-source VRV (or VRF) systems.
Is this strictly for non-profit organizations?
Pilot-Credits IPpc81:Green training for contractors, trades, operators and service workersposted by SIG - Sustainability Main Account on
Having worked for a green building educational non-profit and now working for a green building educational (for-profit) company that also provides LEED administration and consulting....
State DEQ-Listed Brownfield Site - credit denied
NC-2009 SSc3:Brownfield Redevelopmentposted by Michele Otazua on
In our first review, our credit was denied. We are on a zero lot line property with the building occupying the entire site, but the site is listed on the state DEQ register of brownfield sites.
BDC Material & Resource Calculator- Percentage Regional
CS-2009 MRc5:Regional Materialsposted by Suha Hyderabad on
I have a question regarding the BDC Material Tracker, % Regional.
Two new buildings joined by unconditioned walkway
NC-2009 MPR2:Must be a complete, permanent building or spaceposted by P Fanfulik on
I have a new bus garage (maintenance and admin offices) connected to the fuel/wash building by an open air bridge (unconditioned space).
Runoff/Gully Water
NC-2009 WEc1:Water Efficient Landscapingposted by Tamary Alvarez on
Our project's environmental site assessment has documented a gully resulting from the runoff of the adjacent site dumping into our site.
Two lighting related questions
CI-2009 EAp2:Minimum Energy Performanceposted by Ramana Koti on
1. How does one overcome the limitation of number of rows in the ASHRAE Lighting Compliance Documentation PDF form?
Naturally ventilated elevator lobby in mech. ventilated bldg.
NC-2009 IEQc2:Increased Ventilationposted by Lawrence Lile on
I have a very small elevator lobby, which has a little mini-split unit without outside air.