Post a question or comment
Location Filters
Filter by location
Forum
Topic
Replies
Recent

Comms/ data room cooling - Process Energy for LEED

NC-2009 EAc1:Optimize energy performance
posted by  Victoria Watson  on 

Hi all, I am working on a project where the CRAC unit manufacturers have said they don't need to comply with the efficiency requirements of ASHRAE 90.1 for a data room and comms rooms air conditio

3
Tue Nov 11, 2014, 1:59 pm

LEED v4 delay with ACC implications..??

General forums
posted by  Mark Perepelitza  on 

One thought that keeps coming into my mind is how this comes on the heals of the recently announced 'partnership' with ACC. My guess is that this has something to do with the delay.

6
Environmental Stewardship Manager
Tarkett North America
LEEDuser Basic Member
64 thumbs up
Tue Nov 11, 2014, 1:48 pm

All purpose putty

CS-2009 IEQc4.1:Low-emitting materials - adhesives and sealants
posted by  James Emery  on 

I don't believe putty can be categorized as an adhesive or a sealant, but the proposed putty in our project has a VOC of 161 g/l and is being used for filling nail holes and other defects in refurb

3
Principal
Iredale Architecture
LEEDuser Basic Member
0 thumbs up
Tue Nov 11, 2014, 1:23 am

How to model Unit Heaters in Baseline model

NC-2009 EAc1:Optimize energy performance
posted by  Dónal O'Connor  on 

To Whom It May Concern: I'm looking for guidance on how unit heaters, radiant panels and electric heaters that are in the proposed design are modeled in the baseline building.

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Sat Nov 8, 2014, 10:43 pm

Changing from LEEDv4 to LEED 2009

General forums
posted by  P Fanfulik  on 

I registered a project under LEEDv4 (#100038645) because my anticipated completion was past the LEEDv4 sunset date.

9
Founder & CEO, LEED Fellow, BREEAM Fellow
BuildingWise LLC
LEEDuser Expert
224 thumbs up
Fri Nov 7, 2014, 12:05 pm

IEQ4 credit uploads

NC-2009 IEQc4.1:Low-emitting materials - adhesives and sealants
posted by  Shivani Langer  on 

We are trying to submit credits IEQ4.1, 4.2, 4.4 and 4.5 under LEED for schools version 2009.

3
Tue Nov 4, 2014, 3:16 pm

Microturbines and gas rates for energy modeling

NC-2009 EAc1:Optimize energy performance
posted by  Sherman Aronson  on 

For a high rise project the client is considering investing in micro-turbines to generate electrical power on site from natural gas.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Mon Nov 3, 2014, 1:51 pm

More Info on Program is Needed

General forums
posted by  Melissa Wrolstad  on 

There is not very much information released on the program yet, even if you speak directly with representatives of the program and drill them with pointed questions.

4
Founder & CEO, LEED Fellow, BREEAM Fellow
BuildingWise LLC
LEEDuser Expert
224 thumbs up
Fri Oct 31, 2014, 8:31 pm

Press Release Location

General forums
posted by  Suzanne Johnson  on 

I have not been able to find the referenced press release to share with clients. Please let us know where to find it. Thank you.

2
CEO
Green Commons, LLC
LEEDuser Expert
586 thumbs up
Fri Oct 31, 2014, 1:30 pm

Should LPD Area match with Gross Project Square Footage?

CI-2009 EAc1.1:Optimize energy performance - lighting power
posted by  Sunayana Jain  on 

I have a project in which my calculated area by space by space method is slightly more than the area inserted by LEED Admin in "Gross Project Square Footage". Should these numbers match?

3
Thu Oct 30, 2014, 7:43 pm