Historic Bldg Renovation being done in phases, Bldg reuse calcs

NC-2009 MRc1.1:Building Reuse—Maintain Existing Walls, Floors and Roof
posted by  Debra a. Lombard  on 

I'm working on behalf of a GC on a complicated historic renovation and new construction project that's being done in several phases with separate contracts between Owner and GC.

1
Mon Mar 28, 2016, 6:39 pm

WEc2: Time frame for functional reclaimed water systems

NC-2009 WEc2:Innovative Wastewater Technologies
posted by  Brian Bartholomew  on 

Under the Bird's Eye View here for WEc2, there is a citation of LEED Interpretation #10012 made on 05/09/2011 which states "projects may only count future infrastructure such as reclaimed water sys

1
Sat Aug 26, 2017, 9:52 pm

MRc5 Material Tracking/Documentation

CS-2009 MRc5:Regional Materials
posted by  Maggie Hogan Skaug  on 

RE: usgbc.org/leedonline, CS2009 MRc5 I do not see a form or calculator for material tracking or other forms/upload requirements for this credit documentation.

0

searching out no voc floor sheathing and mdf

NC-2009 IEQc4.4:Low-Emitting Materials—Composite Wood and Agrifiber Products
posted by  Phil Vanderloo  on 

I was hoping someone can direct me to a resource, available to Sacramento Ca., for compliant, (no voc or urea formaldehyde), 1 1/8" T&G plywood floor sheathing. Thank You

1
Mon Jun 13, 2016, 12:15 am

Phased Flush Out

Schools-NC-v4 EQc4:Indoor air quality assessment
posted by  Cynthia Kaplan  on 

We have a phased reno/add school project that would prefer to earn IEQ 4 by way of post occupancy flush out.

1
Mon Aug 28, 2017, 2:09 pm

FSC Wood COC

NC-2009 MRc7:Certified Wood
posted by  Andy Prestridge  on 

We have received the FSC invoice for some of our FSC plywood and our subcontractor had it delivered to his shop a few miles away and then brought it to the site.

1
Wed Dec 30, 2015, 7:46 pm

MRpc69 Attainable in the New Construction Project

Pilot-Credits MRpc69:Construction and demolition waste management
posted by  Vanessa Cardona  on 

This credit was readily attainable for a new residential building located in Manhattan. Six streams were recycled by tracking waste throughout the construction phase of the project.

0

Views exculsion for High Bay Window areas

Schools-2009 IEQc8.2:Daylight and Views—Views
posted by  David Sundersingh  on 

We are in the early stages of design for a Career Compact Center, this has 3 workshop areas with high bay windows for natural lighting.

1
Tue Apr 4, 2017, 5:37 pm

Project has all 5 Categories

Schools-2009 WEc4:Process water use reduction
posted by  Sara Zoumbaris  on 

Hi all, My project has all 5 categories installed (dishwasher with racks, pre rinse etc..), however one of the products is above the maximum limit.

1
Wed Nov 25, 2015, 2:38 am

Annual Energy Cost

NC-2009 EAc2:On-Site Renewable Energy
posted by  Sarah Thompson  on 

I am trying to figure out which cost to put in here. Another post said it was savings, although I can't find anything under the credit intent or resources for this specific item.

1
Wed Feb 18, 2015, 10:30 pm