SRI required testing amounts

NC-2009 SSc7.2:Heat Island Effect—Roof
posted by  Anna Korinkova  on 

Hello, could anybody tell me how we can state the number of SRI tests on a project? We intend to place gravel on the roof and provide a concrete parking log.

1
Tue Jan 12, 2016, 5:49 pm

Entryway mats

CS-2009 IEQc4.3:Low-Emitting Materials—Flooring Systems
posted by  Anna Korinkova  on 

Hi everyone, please do you know whether entryway mats - roll out or stabile have to be Green Label certified as carpets?

1
Sat Aug 26, 2017, 8:11 pm

Precertification - Regional credits

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by  Jakub Netolicky  on 

Hello, We are doing precertification but there is no place for Regional Priority, how should we achieve that credit then? Thank you

1
Thu Apr 14, 2016, 2:43 pm

Partially demolished existing building

CS-2009 MRc1:Building Reuse—Maintain Existing Walls, Floors and Roof
posted by  Petra Hajná  on 

Our client has bought a lot with partially demolished existing building listed on national heritage fund list. So we need to preserve what has left - portion of exterior walls.

1
Thu Jan 19, 2017, 2:19 pm

Precertification credits online

CS-2009 WEc3:Water Use Reduction
posted by  Jakub Netolicky  on 

Hello, at the moment we are doing precertification, when I want to attemt some credits on website LEEDonline, some credits remain 0, therefore, we have only few points in total.

1
Thu Jan 19, 2017, 2:03 pm

preliminary design review - chiller - Baseline

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by  jana Paulech  on 

Hi, I would like you to ask for helping me with one LEED issue. We were doing energy model and we have received comments to our model, which one of them is this one: 8.

1
Wed Dec 14, 2016, 3:12 pm

LEED EBOM

Pilot-Credits EQpc78:Design for active occupants
posted by  Lukas Urban  on 

Hi! Can we use this Pilot-Credit in a LEED EBOM project? Our staircase meets almost all the conditions. Thank you.

0

LCA Part C – End of Life

NC-v4 MRc1:Building life-cycle impact reduction
posted by  Petr Vogel  on 

The credit says cradle to grave so it is obvious that this part has to be included. Is there any guidance how should it be included?

0

Underground infiltration tank

NC-v4 SSc4:Rainwater management
posted by  Frantisek Macholda  on 

Hello, our project is constrution of the new storage hall on the place of the previously existing old one. (Demolition + new construction).

1
Wed Aug 9, 2017, 7:53 pm

Local voluntary cleanup program - definition

NC-2009 SSc3:Brownfield Redevelopment
posted by  Anna Korinkova  on 

Under Option 1 of the credit, we can pursue EITHER the ASTM E1903-97 Phase II Environmental Site Assessment OR the 'local voluntary cleanup program'.

3
Mon Mar 13, 2017, 4:52 pm