Renewable Energy - Confirmation of Renewable Attribute Ownership
CS-v4.1 EAc5:Renewable Energyposted by Levi Jimenez on
We have a site with a substantial solar array that is owned by the building owner. The LEED Credit form requires uploaded supporting documentation as follows: "upload confirmation
Base case System-8
NC-v4 EAp2:Minimum energy performanceposted by Rathnashree Bharadwaj on
We are working on a project where there are multiple AHU's in the single floor. Few AHU's have MERV-14 filtration and in built HRW. The rest of the AHU's only has MERV-8.
Minimum Skylight Fenestration Area
CS-v4.1 EAp2:Minimum Energy Performanceposted by Narguess Kh on
I am working on a data center and planning to use Prescriptive provisions of Sections 5 through 10 to comply with energy credit. The data hall is greater than 232 m2 but they are not occupied.
solar PV Farm adjacent to Datacenter
Data-Centers-NC-v4.1 EAp2:Minimum Energy Performanceposted by S S on
Hello Everyone,
Greetings!
The proposed Datacenter building is intended to achieve LEED certification under LEED v4.1 BD+C Rating system - Datacenter
Product meeting multiple MRc4 methodologies
NC-v4 MRc4:Building product disclosure and optimization - material ingredientsposted by Van Jomel Garcia on
Hi! Has anyone encountered a product that complies with more than one compliant MRc4 Methodologies?
Option 2 Strategy E for an Atrium area - No ceiling areas (Open to roof deck above)
NC-v4 EQc6:Interior lightingposted by John Covello on
Hello.
For Option 2, Strategy E.
Can we consider the cafe yard as an open space?
NC-v4 SSc3:Open spaceposted by Dzu Pham on
Hello,
I have a question.
Our project have a cafe space outdoor. Can we consider it as an open space? Can you give me some suggestion?