Issue with LEED Forms

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by  Sara Zoumbaris  on 

A few projects that I am as team member on have recently experienced a LEED Online form issue where information "disappears." I am curious if other folks have had this issue and how have you have a

4
Director of Sustainability
Fentress Architects
LEEDuser Expert
224 thumbs up
Thu Oct 6, 2016, 3:03 am

Laundry Chemical

EBOM-v4 EQc7:Green cleaning - products and materials
posted by  VISHESH AGARWAL  on 

Cleaning and Degreasing- CCD-110 is this credit include the laundry cleaning product come under the cleaning and degreasing category.

2
Wed Oct 5, 2016, 5:47 pm

hand watering for irrigation

EBOM-2009 WEc3:Water Efficient Landscaping
posted by  cathy keagle  on 

What irrigation efficiency should be used for hand watering?

2
Wed Oct 5, 2016, 5:00 pm

carpet tile adhesive tabs

NC-2009 IEQc4.3:Low-Emitting Materials—Flooring Systems
posted by  Elizabeth Eason  on 

We have carpet tiles attached to the floor with adhesive tabs at the corners rather than with a fluid adhesive. Are the adhesive tabs to be listed in the adhesives and sealants table?

2
Wed Oct 5, 2016, 1:54 pm

Green Power Contract through vendor

Retail-NC-v4 EAc7:Green power and carbon offsets
posted by  Joanna Ruiz  on 

I am working with a corporate client, who uses a third party company to seek and procure all their utility contracts.

3
Default Avatar
Project Manager, LEED AP
Wallin/Gomez Architects
LEEDuser Basic Member
0 thumbs up
Wed Oct 5, 2016, 1:21 pm

Authority having Jurisdiction

NC-v4 EAp1:Fundamental commissioning and verification
posted by  Pam Lynch  on 

I just took a LEED GA pratice exam and do not understand the answer to this question: The ‘Authority having Jurisdiction’ is responsible for which of the following? a) Completing the commissioning

2
Default Avatar
VP of Innovation
Sustainable Investment Group
LEEDuser Basic Member
110 thumbs up
Tue Oct 4, 2016, 9:28 pm

Contract through Design Team - conflicting information

NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Rory Cousino  on 

I am going to ask a question that is probably been answered before - but I cannot find the simple answer. Can the CXA be contracted through / to the Design Team?

4
Tue Oct 4, 2016, 9:16 pm

FSC-certified bamboo

NC-v4 MRc3:Building product disclosure and optimization - sourcing of raw materials
posted by  Jason Grant  on 

LEED Interpretation ID# 2535 ruled that, under LEED 2009, FSC-certified bamboo could be counted under both MRc6 (Rapidly Renewable Materials) and MRc7 (FSC Certified Wood).

4
Editorial Director
BuildingGreen, Inc.
LEEDuser Expert
159 thumbs up
Tue Oct 4, 2016, 4:01 pm

Definition of "bus line"

NC-2009 SSc4.1:Alternative Transportation—Public Transportation Access
posted by  Michael Kennedy  on 

Our project is on a college campus that is within 0.15 mile of a bus stop. It is served by one bus system. It's a public, not student-only system.

2
Senior Principal | Director of Sustainability Integration
SmithGroup
LEEDuser Expert
43 thumbs up
Tue Oct 4, 2016, 12:20 pm

Ceramic Tile not exempted any longer

NC-2009 IEQc4.3:Low-Emitting Materials—Flooring Systems
posted by  Melissa Merryweather  on 

I've submitted several projects over the past few years, all outside the US where ceramic tile is much more common and will always be locally produced.

2
Tue Oct 4, 2016, 3:01 am