Waiver for Quantity Requirement

NC-2009 SSc6.1:Stormwater Design—Quantity Control
posted by  Tim Setala  on 

We have a project where infiltration is not possible as the soils are D type.

1
Thu May 2, 2013, 5:26 pm

Chiller

NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Saju Varghese  on 

Should the chiller be considered part of the commisioning and M&V metering even if it's serving other tenants as well?

1
Wed May 1, 2013, 2:50 pm

Chiller

CI-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Saju Varghese  on 

Does a chiller have to be considered in commisioning even if the chiller is serving other tenants as well?

1
Mon Nov 4, 2013, 4:58 pm

Divisions

CI-2009 MRc4:Recycled Content
posted by  Mike D  on 

Where can I find the list of Divisions stating which materials are under which Divisions? thanks!

1
Wed May 1, 2013, 4:37 pm

Single possibly non-compliant adhesive

CI-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealants
posted by  Eric Thompson  on 

I'm working on a project in Norway and it is very difficult to get information from the contractor who is resistant to cooperation. It appears that one of the adhesive products is non-compliant, t

1
Tue Jun 11, 2013, 1:54 pm

LEED® Certification Agreement

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by  Albert Sagrera  on 

Once finalized the justification of credits, and uploaded the information to begin the process of Design Preliminary Review, in the section Overview, we get this message: " Your selections do not m

1
Fri May 3, 2013, 9:41 pm

HERS equivalency in international context

ND-v2009 GIBc2:Building energy efficiency
posted by  Daniel Costantino  on 

Hello: are there any recommended approaches for equivalency with HERS ratings in international contexts? Thank you, Daniel

1
Thu May 2, 2013, 3:25 pm

MRc5 Calculator Question

Healthcare-v2009 MRc5:Furniture and medical furnishings
posted by  Catherine Blakemore  on 

My project is going for Option 1 of the MRc5 credit.

1
Thu Oct 24, 2013, 7:49 pm

Zero Lot Line Development

EBOM-2009 SSc3:Integrated Pest Management, Erosion Control, and Landscape Management
posted by  Ralf Lehmann  on 

If the project has no outside facilities, is the credit still available? For example I have dove defense on the roof. Thank you!

1
Wed Jul 31, 2013, 4:13 pm

Regional Credits in Canada?

Healthcare-v2009 RPc1:Regional priority
posted by  Ed Clark  on 

Hi, I am curious as to how to assess regional priority credits for a project in Vancouver, BC. Thanks, Ed Clark

1
Fri May 3, 2013, 6:09 pm