Appeal Design Credits After Construction Review has begun?LEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Garrett Ferguson on Jul 22, 2015, 3:58 pm
I have a CS 2009 project where 2 credits were denied in the Design Final Review. We are sitting at 42 points if all goes as planned. While I can appeal one of the credits and pursue it through... Last reply: Garrett Ferguson, Jul 22, 2015, 4:05 pm |
|
Submission of Design Cr. during Constr. Final Rev. f. 2nd roundLEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Lise Dannesboe on Jun 28, 2015, 7:40 am
Hi! |
|
Want to Appeal Denied SSc4.3LEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Rachel Manoguerra on Jun 17, 2015, 1:39 pm
We have submitted our design review and we got the report back. We want to appeal the about mentioned credit. Last reply: Rachel Manoguerra, Jun 17, 2015, 5:02 pm |
|
Timeline for reviewLEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Lawrence Lile on Jul 28, 2014, 9:19 pm
We have just received our review for combined D&C. What is the deadline to respond to the reviewer's comments? Last reply: Charles Nepps, Jun 16, 2015, 4:03 am |
|
Can I lock the credits not to be touched by other team members?LEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Matt Dem on May 22, 2015, 7:04 pm
Is there any feature in LEED online to lock the credits not to be changed by other team members ? I was about to submit for design final submission but then the owner postponed it for one... Last reply: Charles Nepps, May 24, 2015, 6:27 pm |
|
Filed (2)exemp. performance credit under (1) ID in case one failLEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Matt Dem on May 22, 2015, 2:14 pm
Hi, ID credit form shows the first exemplary credit but I... Last reply: Matt Dem, May 22, 2015, 2:52 pm |
|
Can I defer any ID credit to submit it w/ construction package?LEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Matt Dem on May 22, 2015, 8:34 am
Hi, I previously filed an innovation credit with my design preliminary submission and received an comment from... Last reply: Matt Dem, May 22, 2015, 9:23 am |
|
Where do I upload the response report for Design Final Package?LEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Matt Dem on May 22, 2015, 8:35 am
We, as a team are getting ready to submit our design final submission and prepared a report to respond to each individual comments made by... Last reply: Matt Dem, May 22, 2015, 9:22 am |
|
Appeal after second reviewLEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Johnathan Woodside on May 4, 2015, 4:04 pm
I guess my question is; does the second review include review of changes made as a result of comments made during the second review? In other words; Design prelim; Comments made by reviewer;... Last reply: Charles Nepps, May 4, 2015, 4:54 pm |
|
Reopening one path of LEED-CI SSc1.2 in Construction ReviewLEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Susan Di Giulio on Mar 27, 2015, 2:01 pm
In preliminary design review, we had attempted the Brownfields point, which is an option in SSc1.2.1, as well as 4 other points in that credit. The reviewer responded that we needed to show a... Last reply: Marcus Sheffer, Apr 28, 2015, 10:28 am |