Form Releasing Agents VOC Requirements

NC-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatings
posted by  Samantha Nourse  on 

I have a subcontractor proposing to use a Form Releasing Agent with a VOC level of 445 g/L. I have yet to find a hard-fast requirement for a VOC max. content for this LEED Credit.

0

SSc5.1 Disturbance Parameter Clarifications

NC-2009 SSc5.1:Site Development—Protect or Restore Habitat
posted by  Hal Marvin  on 

I assume that stormwater drainage pipes and appurtenances count as utilities and will be allowed the 10 or 15 foot disturbance buffer depending on diameter?

1
Mon Feb 24, 2014, 1:34 pm

Zoning Minimum parking requirements

CI-2009 SSc3.3:Alternative Transportation—Parking Availability
posted by  Jessica Miller  on 

My office is moving to a mixed use space so we will be SSc3 case 1, less than 75% of the building.

1
Sat Jul 26, 2014, 5:27 am

WEc1: Only one fixture in CI Space

CI-2009 WEc1:Water Use Reduction
posted by  Susan Di Giulio  on 

Dear Tristan, If you only have one fixture, a faucet in staff lunchroom, in a CI project, and it does meet the goal of 20% better than code, i.e. 1.5 gpm. Then do you gain this credit?

1
Sun Feb 23, 2014, 1:10 am

BD+C exam question

NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehicles
posted by  Farah A.  on 

An owner has decided to provide low-emitting vehicles for a car sharing program in the new construction project.

1
Mon Feb 24, 2014, 12:59 pm

LEED exam question

NC-2009 EAc2:On-Site Renewable Energy
posted by  Farah A.  on 

A project team is looking to pursue an ID credit on their new office building. The annual building energy cost for their 400,000 square foot project is $15,120.

1
Sun Feb 23, 2014, 9:47 pm

Low-Emitting

NC-2009 IEQc4.4:Low-Emitting Materials—Composite Wood and Agrifiber Products
posted by  Farah A.  on 

Are wall-coverings and porcelain tiles covered under Low-Emitting materials credits?

1
Mon Feb 24, 2014, 1:01 pm

For Hotel Project

EBOM-2009 IEQc2.2:Controllability of Systems—Lighting
posted by  Boon Wah Chong  on 

As it wasn't mentioned anywhere. I would like to enquire, for Hotel project, if there are individual switches for each light or set of lights.

1
Mon Mar 31, 2014, 11:54 pm

Exclude existing parking with certification of building addition

Schools-2009 SSc7.1:Heat Island Effect—Nonroof
posted by  Larry Turbes  on 

We are pursuing LEED certification for a 9,000 square foot addition to a 35,000 square foot school. The existing school will not be certified.

1
Mon Feb 24, 2014, 6:24 pm

smoking space in annex

CS-2009 IEQp2:Environmental Tobacco Smoke (ETS) Control
posted by  Noriko Nagazumi  on 

Hello, Our project has a 1-story annex building which is separated from the base building and includes two types of spaces, toilet / shower booth space and smoking room.

0