Topic | Recent |
---|---|
Should the soil be previously disturbed, before the owner starts to do anything with it?CS-v4 SSc2: Site development - protect or restore habitatposted by Marine Petrosyan on Oct 4, 2023, 3:17 am
Hi, All! The Site Development - Protect or Restore Habitat credit requires, that the calculations are done with the previously disturbed land. I am planning to calculate the area of... Last reply: Afogreen Build, Apr 22, 2024, 9:02 pm |
|
Option 1: General Contractor, (and? or?) Subcontractor and TradesPilot-Credits IPpc90: Social equity within the operations and maintenance staffposted by Vanessa Hostick on Apr 22, 2024, 6:36 pm
In reviewing the language for Option 1 item 2, it is not clear if this language applies to all trades under the construction contract. I typically work on large projects where the general... |
|
Previous Buildings Demolition activitiesNC-v4.1 MRc5: Construction and demolition waste managementposted by Carla Joan Carrasquillo on Jun 23, 2023, 9:55 am
I'm working with a project that comprehends various buildings (~20), from which only 10 will be certified. The complexity of the project is related to the demolition activities that will take... Last reply: Dave Hubka, Apr 22, 2024, 3:28 pm |
|
Innovative StrategiesPilot-Credits SSpc154: Heat Island Mitigation with Cool Wallsposted by Dulce Solis on Apr 22, 2024, 2:31 pm
Has anyone utilized innovative design approaches or unique cool wall materials for Heat Island Mitigation (SSpc154)? We're interested in learning about any unconventional... |
|
Optimizing Cool Wall DesignPilot-Credits SSpc154: Heat Island Mitigation with Cool Wallsposted by Dulce Solis on Apr 22, 2024, 2:26 pm
What strategies or design considerations have you found effective in maximizing the heat island mitigation benefits of cool walls while minimizing potential negative impacts such as glare,... |
|
Measuring SuccessPilot-Credits SSpc154: Heat Island Mitigation with Cool Wallsposted by Dulce Solis on Apr 22, 2024, 2:23 pm
How have you evaluated the performance and effectiveness of cool walls in mitigating the urban heat island effect within your projects? What monitoring tools, metrics, or post-occupancy... |
|
LEED Dedicated Form for CS-v4.1 IPc1- Integrative ProcessCS-v4.1 IPc1: Integrative processposted by on Apr 22, 2024, 11:26 am
On LEED Online the form available for download appears to be for v4 only, and isn't specific to Core and Shell projects. Is there a designated C+S form for the Integrative Process credit, and is... |
|
option 2, additional source control and monitoringCS-v4 EQc1: Enhanced indoor air quality strategiesposted by James Cai on Apr 21, 2024, 11:27 pm
Hi, Can the installation of PM2.5 sensor meet this requirement? |
|
IPpc144 Social Equity within the Supply ChainNC-v4 INc1: Innovationposted by Allen Cornett on Aug 21, 2023, 6:18 pm
Is there a list of companies/materials known to contribute to the IPpc144 Social Equity within the Supply Chain pilot credit? Last reply: Douglas Flandro, Apr 22, 2024, 10:05 am |
|
Restaurant and KitchenNC-v4 EQc1: Enhanced indoor air quality strategiesposted by Omar Elrawy on Dec 1, 2018, 9:24 am
I need to know if I have to apply interior cross-contamination prevention on a kitchen and a restaurant at my NC office building or not? Last reply: Afogreen Build, Apr 21, 2024, 9:04 pm |