Are Base/Subbase Aggregate Materials part of Materials Cost?

NC-2009 MRc5:Regional Materials
posted by  Matthew Martin  on 

I have not seen this question about base/subbase addressed here yet. I have read the comment fill materials are part of 31 2000 Div.

2
LEED-AP BD+C
GREENSQUARE
LEEDuser Expert
261 thumbs up
Mon Aug 8, 2016, 3:48 pm

Broken Bricks, Tiles and waste materials

NC-2009 MRc3:Materials Reuse
posted by  Yusuf Turab  on 

We have used large quantities of waste materials procured from manufacturers. We have procured waste material like broken bricks form the brick manufacturer.

3
Managing Director
InHabit & BuildScape
LEEDuser Basic Member
18 thumbs up
Mon Aug 8, 2016, 1:05 pm

Select Fill

NC-2009 MRc5:Regional Materials
posted by  Allen Cornett  on 

Can select fill mined within the LEED boundary be counted as a regional material?

3
Assistant Site Superintendent
QBS, Inc.
LEEDuser Basic Member
3 thumbs up
Sun Aug 7, 2016, 7:40 pm

Tenant is installing the entire energy systems at the building

CS-2009 EAc5.2:Measurement and Verification—Tenant Submetering
posted by  Michael Wahjudi  on 

Hi all, we have building where the tenant is installing the entire energy related system (ACMV, lighting, etc). The landlord only provide land and structural of the building.

3
Fri Aug 5, 2016, 10:43 pm

Using v4 NPDc5 on LEED ND v2009

ND-v4 NPDc5:Reduced parking footprint
posted by  Gwen Corrie  on 

We have a registered LEED ND v2009 project. Our SSLc4 does not comply (we are shy of the needed short-term bike racks and showers).

4
Fri Aug 5, 2016, 4:01 pm

LCA and EPDs

NC-v4 MRc3:Building product disclosure and optimization - sourcing of raw materials
posted by  NESLIHAN AKSOY  on 

Buildings LCA is conducted to measure the impact of building materials..as well as building use etc.

2
LFA, RESET ASP, WELL Faculty, LEED Fellow
Wight & Company
LEEDuser Expert
6 thumbs up
Fri Aug 5, 2016, 12:42 pm

Are GoO fulfilling EAc6 credit?

NC-2009 EAc6:Green power
posted by  Francesco Allaix  on 

GoO (Guarantees of Origin) are European equivalent to United States' REC.

5
Fri Aug 5, 2016, 10:08 am

Best Methods for Conducting a Drawing Review

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by  Melissa Estrada  on 

My sustainability consulting firm has been conducting the con docs (drawing) reviews for our clients for LEED compliance, but the method we have been using is not the most streamlined.

4
NH Green Consulting
LEEDuser Premium Member
80 thumbs up
Thu Aug 4, 2016, 9:31 pm

cradle to gate scope?

NC-v4 MRc2:Building product disclosure and optimization - environmental product declarations
posted by  Erin Holdenried  on 

Does the compliance with the ISO 14025 standard automatically include cradle to gate scope? Or is the scope stated separately in the product EPD?

3
Default Avatar
Sustainable Design Director
Bell Architects
LEEDuser Premium Member
40 thumbs up
Thu Aug 4, 2016, 4:18 pm

Integrative Process (IP) Guide 2.0

NC-v4 IPc1:Integrative process
posted by  Vitor Tosetto   on 

Please, someone knows where can I buy the Integrative Process (IP) ANSI Consensus National Standard Guide© 2.0? In ANSI's webstore I found v1.0 only.

10
Thu Aug 4, 2016, 3:37 pm