What about embedded Adhesives

NC-2009 IEQc4.1: Low-emitting materials - adhesives and sealants
posted by Maya Karkour on Jul 18, 2011, 10:48 am

Hello,

Assuming the building is purchasing pre-made...

Last reply: David Posada, Jul 18, 2011, 12:53 pm

ACP

Pilot-Credits PC1: Life-Cycle Assessment (LCA) of Building Assemblies and Materials 
posted by Whit Faulconer on Jul 18, 2011, 10:34 am

Thanks Batya, and Susan hit the nail on the head. Proposing that at some point an LCA based credit could be an ACP for some of the MR Credits is tricky for many reasons. We are working to...

Who may purchase RECs?

Schools-2009 EAc6: Green Power
posted by James Keohane on Jul 17, 2011, 12:52 pm

Is acceptable for a member of the design team or construction team to purchase RECs?

May a project team purchase RECs using project contingency funds directed by Owner?

Last reply: Marcus Sheffer, Jul 18, 2011, 8:21 am

Daylighting Calculations Out Of Range

NC-2009 IEQc8.1: Daylight and views - daylight
posted by Eesmyal Santos-Brault on Jul 14, 2011, 7:25 pm

We are working on a mixed use commercial and residential building using OPTION 2: Prescriptive Path where we calculated 0.150

Last reply: Eddy Santosa, Jul 15, 2011, 6:28 pm

Prescriptive Method: Skylights

NC-2009 IEQc8.1: Daylight and views - daylight
posted by Kash Boodjeh on Jun 15, 2011, 12:17 pm

Hello,
We are pursuing the Prescriptive Method for this credit, using skylights. I am not sure how to answer the first two measurements requested on the LEED form (the distance between...

Last reply: Eddy Santosa, Jul 15, 2011, 6:24 pm

a mistake in the daylight formula of the available spreadsheet

NC-2009 IEQc8.1: Daylight and views - daylight
posted by Eddy Santosa on May 24, 2011, 8:03 pm

Please be careful and aware when you use the available spreadsheet:
Daylight and Views Calculator released 11152010.xls . The spreadsheet contains a mistake in its skylight roof coverage...

Last reply: Eddy Santosa, Jul 15, 2011, 6:22 pm

Stormwater Management

EBOM-2009 SSc6: Stormwater Quantity Control
posted by Randy Walsh on Jul 15, 2011, 4:54 pm

Does installation of mechanical filter media into the storm drain help meet this requirement? (Flogard curb filter inlet)

Last reply: David Posada, Jul 15, 2011, 5:17 pm

Negative Pressure Differential Requirement

CS-2009 IEQc5: Indoor Chemical and Pollutant Source Control
posted by Maya Karkour on Jun 21, 2011, 3:31 am

Dear all,

One of the credit requirements is that:
"The pressure differential with the surrounding spaces must be at least
5 Pa on average and 1 Pa at a minimum when the doors...

Last reply: Allison Beer McKenzie, Jul 15, 2011, 5:05 pm

Walk-off mat size

Schools-2009 IEQc5: Indoor Chemical and Pollutant Source Control
posted by Will Britten on Jul 15, 2011, 3:04 pm

The requirement for walk-off mats is vague in regards to size of mat required. I think they are typically 4'x6' or in that range, does the 10 foot requirement only apply to permanently installed...

Last reply: Tristan Roberts, Jul 15, 2011, 3:51 pm

LEED CI parking for company vehicles

CI-2009 SSc3.3: Alternative transportation - parking availability
posted by Natalie Ng on Jul 15, 2011, 6:24 am

The project would like to look into Case 1 option 1. The tenant included carparking spaces into the lease. However, all the parking will be occupied by company vehicles which will only travel...

Last reply: David Posada, Jul 15, 2011, 2:42 pm