Forum quick links
Served by part of large air-conditioning system
CI-2009 IEQp1:Minimum IAQ Performanceposted by Shirong Meng on
If the project spaces are served by a large VAV system which has mixing of central Outside air inlet and recirculation air, but the VAV system is also serving other tenant spaces.
90.1 Envelope Requirements
NC-2009 EAp2:Minimum Energy Performanceposted by Ruben Porter on
I'm trying to model a wood framed 4 story multifamily building, and the client wants to go without continuous insulation which is what's called for on table 5.5-4, resulting in a higher U value th
Appeal submitting period
posted by eirini matsouki on
hi there, one of our porjects is been denied a pre-requisite (EAp2) during the final design review and hence the project has entered the appeal process (enetring the 'design appeal review' - within
Covered Loading Dock - What is a parking space?
NC-2009 SSc7.1:Heat Island Effect—Non-Roofposted by Richard Woodward on
We are working on an urban alteration project which extends an existing building to cover an exterior loading dock, enclosing it within the new building.
SSC1 Path 5: Heat Island Effect: Roof
CI-2009 SSc1:Site Selectionposted by Elliot Young on
I am working on a project with an existing ballasted roof & am wondering if we could get this credit.
Base case system for high equipment loads spaces
NC-2009 EAp2:Minimum Energy Performanceposted by Nandana Kumar on
The project is a 67000 sqft, six floored building. There are rooms with high equipment loads of greater than 20W/sft . The total area of these type of rooms adds up to 14,000 sqft.
Water waste
NC-2009 MRc2:Construction Waste Managementposted by Karim Farah on
During coentsruction, a project has a major amount of water waste (more than 50% of the total amount of the waste generated by one production unit), this quantity of water is a result of the produc
Tap for bar counter
Retail-CI-v2009 WEp1:Water use reductionposted by Eddy Tsang on
Should i include the tap for the bar counter in the water use reduction calculation?
Process energy
NC-2009 EAp2:Minimum Energy Performanceposted by Graham Langton on
Regarding what is taken as a process energy.
Can the CxA be involved in the thermal model of EAp2?
NC-2009 EAc3:Enhanced Commissioningposted by Maya Karkour on
Dear All, We are consulting for a large LEED-NC tower. The thermal model for EAp2 / EAc1 were undertaken by a company independant from the design team.