Forum quick links
Thanks for the responses so
posted by Michael Zagorski on
Thanks for the responses so far... Please keep them coming!
Sort chiller heat pump in ASHRAE 90.1-2007
CS-2009 EAp2:Minimum Energy Performanceposted by Diego Escalona on
Hello all, I'm participating in a project of a building of 20 floors of offices, of which the first corresponds to shops and entrance hall.
LEED NC- ID credits- Green Cleaning for NC?
NC-2009 IDc1:Innovation in Designposted by Melissa Decatur on
Currently we are exploring ID credits for our two projects under NC. To date the Education credit complies with our project and NC.
Bike Racks and FTE
NC-2009 SSc4.2:Alternative Transportation—Bicycle Storage and Changing Roomsposted by Ann Wright on
We are working on a CHP. Should we count patrol officers as FTE or Visitors. They report to work then take a patrol car during their shift work that is patrolling the highway.
GBCI defines a minimum floor area requirement to earn MRc9
EBOM-2009 MRc9:Solid Waste Management—Facility Alterations and Additionsposted by John McFarland on
There's been a lot of discussion and questions in the past regarding whether there is some minimum amount of work required to earn this credit and MRc3.
LEED ND GIB credit 4 - Water efficient landscaping
posted by Tyler Baker on
I am working on a residential redevelopment in a mature inner suburb.
RE:62MZ calc. spreadsheet Vdzd & Ds inputs
CI-2009 IEQp1:Minimum IAQ Performanceposted by Bobby Ghataura on
In the 62MZ calc, i created zones that have heating and potentially critically zones, but im having an issue with the results; for Vdzd, i enter the airflow rate that corresponds to the minimum VAV
Opt. 2: Average density residential area
CI-2009 SSc2:Development Density and Community Connectivityposted by Marco Abdallah on
We have a project in the center of Paris where we want to pursue option 2 of this credit.
Baseline system selection
NC-2009 EAp2:Minimum Energy Performanceposted by Jane Long on
I'm modelling a European Industrial project where nearly a 5th of the floor area is a specialist process area, similar to a clean room or laboratory, however used for industrial processes, in use 2
Regularly Occupied Spaces
NC-2009 IEQc8.2:Daylight and Views—Viewsposted by Amit Vaswani on
Hey Guys, We're designing a facility with Classrooms and Private Offices for 6 regularly occupied employees.