Clarification needed on "New" vs "Old"

CI-2009 EAc1.4:Optimize Energy Performance—Equipment and Appliances
posted by  Monika Mickute  on 

Hi, We moved into a new building (CAD production, Document management, and large scale plotting business), which we are certifying under LEED CI.

0

Audit reccommendation to turn off zone

EBOM-2009 WEc3:Water Efficient Landscaping
posted by  SIG - Sustainability Main Account  on 

We performed a full audit of the irrigation system and some of the findings were to turn off zones that are watering established plants or mulch areas.

1
Fri Jan 20, 2012, 6:29 pm

Site Boundary

General forums
posted by  Cynthia Estrada  on 

Phoebe, The buildings must be physically distinct, and have unique addresses or names among other issues according to the Minimum Program Requirements Supplemental Guidance.

0

Super 8 Motel - comply with 10 units per acre

NC-2009 SSc2:Development Density and Community Connectivity
posted by  Thomas Boyd  on 

Can a super 8 motel be used as a residence documenting 10 units per acre if the operator is leasing rooms on month to month basis?

1
Thu Jan 19, 2012, 9:39 pm

EPP certification for proof of recycled content?

NC-2009 MRc4:Recycled Content
posted by  Renee Shirey  on 

Has anybody ever had an issue with using an EPP certified product to gain recycled content for a project?

1
Thu Feb 2, 2012, 12:16 am

Design Appeal and Construction Submittal

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by  J Morrison  on 

We had run into the issue that before we accepted the Design appeal we could not upload anything to our project site.

1
Wed Jan 25, 2012, 3:04 pm

Exemplary Performance

NC-2009 MRc7:Certified Wood
posted by  J Morrison  on 

Have been having difficulty uploading documents for this credit. I called the 800 number and they said that they were having technical difficulties and to try again later.

1
Mon Jan 23, 2012, 7:36 pm

Appeals

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by  J Morrison  on 

Is there a limit to the number of appeals? The cost is so much per credit on appeals if I understand correctly?

1
Wed Jan 25, 2012, 3:09 pm

Cost info on LEED EBOM

General forums
posted by  James Doyle  on 

For LEED EBOM cost info look at info in document from Environmental Defense Fund / edf.org titled Climate Corps Handbook Energy Efficiency Investment Opportunities in Commercial Buildings / FOURTH

0

Fluid Applied Air Barriers

Schools-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatings
posted by  Nilo Regojo  on 

We are a General Contractor working on a school project and the specs require submittal of product data for the air barrier as part of IEQc4.2.

1
Fri Feb 17, 2012, 6:44 pm