Post a question or comment
Filter by location
Forum
Topic
Replies
Recent

Case 2

EBOM-2009 IEQp1:Minimum IAQ Performance
posted by  AAME User  on 

If the 62MZ calculator reveals that the critical zone is a zone with cooling only (with a min of 0), is that an appropriate reason to pursue Case 2?

1
Wed Oct 3, 2012, 3:40 pm

About Table 1.Standard VOC Limits

NC-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatings
posted by  Albert Sagrera  on 

Hi, about the table 1. Standard VOC Limits, which values ​​we might use, Ceiling Limit or Effective Date? Thank you,

1
Tue Jul 17, 2012, 7:51 pm

Prescriptive approach - adjusting VLT for an overhang

NC-2009 IEQc8.1:Daylight and Views—Daylight
posted by  Ramana Koti  on 

Greetings all. One one of our LEED projects, we're using the prescriptive approach of VLT*WFR falling within the range of 0.15 and 0.18.

1
Wed Jun 27, 2012, 8:43 pm

Dorm Rooms

EBOM-2009 IEQc2.2:Controllability of Systems—Lighting
posted by  American University  on 

We're pursuing EB:O&M on several campus buildings including residence halls, classroom buildings, and office buildings.

1
Wed Sep 5, 2012, 12:56 am

Air-tight Drywall Approach/Compartmentalization &Sprinkler Heads

LEED for Homes (LEED-H) Forum
posted by  Kathy Kahill  on 

What are people doing out there for sealing quick-response sprinkler heads in mid-rise projects? I've been told that the gasket approach cannot be used with quick-response heads.

0

ID Credit for New Construction Projects

EBOM-2009 WEc1:Water Performance Measurement
posted by  Heather Holdridge  on 

Has anyone had any success using this as an ID credit for a new construction project?

0

Path 6

CI-2009 SSc1:Site Selection
posted by  Nelina Loiselle  on 

Does anyone have a sample of a sequence of operations narrative? I am not sure what they'd like to see.

1
Thu Jul 5, 2012, 3:49 pm

Entryways system disntance 10ft

CS-2009 IEQc5:Indoor Chemical and Pollutant Source Control
posted by  gabriel Morales  on 

Hello, architecture according to our main lobby, meeting with the distance of 10ft mat we complicated for users coming from the parking lots. The design team has proposed installing a section of

1
Fri Jul 13, 2012, 5:34 pm

Interpretations Database

General forums
posted by  Marcus Sheffer  on 

I was scanning a comment I made last year after the new database was released and wanted to offer some praise to the the current version.

0

Performance Requirements for Water Heating Equipment

NC-2009 EAp2:Minimum Energy Performance
posted by  Oliver Lange  on 

Hello, our project has 40 electrical table top water heaters. The electrical input is 2 kW and 5 liter storage. What is the right way for modeling the baseline builing water heating equipment?

1
Fri Jun 29, 2012, 6:13 am