Minimum occupancy requirements for projects pursuing LEED NC
posted by Guillermo Hernandez Espinoza on
Hi. The project is registered under LEED BD+C: New Construction v2009. Is there any Addenda that perhaps changed what is required for a project pursuing LEED NCv2009 from 50% to 0%? (For such a
ASHRAE 90.1-2007 - 6.4.3.1.1 COMPLIANCE CRITERIA
CI-2009 EAp2:Minimum Energy Performanceposted by RICARDO HERNANDEZ on
Does anyone know how stringent is the criteria to achieve compliance with the 6.4.3.1.1 Zone Thermostatic Controls for a Commercial Interiors?
Redrawing Project Boundary AFTER Initial Review
Healthcare-v2009 MPR3:Must use a reasonable site boundaryposted by C.M. G. on
Hello, We are currently preparing our project for final review, and realized that that we drew our project boundary in such a way that disqualifies us from SSc8.
Where are the Import Facility Data Templates?
NC-2009 MPR6:Must commit to sharing whole-building energy and water usage dataposted by Lewis Hewton on
Can somebody please direct me where to find the 'import facility data' templates on the Energy Star website?
Does new LEED online open now?
posted by Jorng-ren Chern on
It is Dec. 13 now and I still cannot find the webpage of LEED online V4. Can anyone provide the link? Thanks.
Utility tariff - an accepted DR strategy?
Data-Centers-NC-v4 EAc4:Demand responseposted by H.K.C.B. Heendeniya on
Hi, Our electricity tariff for industries has a time based component and peak demand (kVA) component.
Naturally Ventilated Underbuilding Parking Garage and 62.1
NC-2009 EAp2:Minimum Energy Performanceposted by Jean Marais on
62.1 has an exahust requirement for mechanically ventilated Parking garages (Table 6-4), with an exception C - no ventilation required if two or more sides comprise walls that are at least 50% open
Tenant submetered water use in CS scope?
NC-2009 WEp1:Water Use Reduction—20% Reductionposted by Jukka Akselin on
In our shopping mall CS project the all water fixtures in tenant spaces are controlled by tenants (shops + restaurants) and the owner has no control over the fixtures.
Commissioning Agent Qualifications
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Rick Alfandre on
Qualifications for CxA state they must have documented commissioning authority on at least 2 building projects. Is there any commissioning authority experience outside of LEED CxA experience tha
Adjustable shower head
NC-2009 WEp1:Water Use Reduction—20% Reductionposted by Nelina Loiselle on
We received a reviewer comment saying since we had an adjustable shower head we would have to assume the highest gpm setting.