Lighting Power Density Using The Building Area Method
NC-2009 EAp2:Minimum Energy Performanceposted by Curtis Clark on
How do you apply Building Area Method (ASHRAE Table 9.5.1) to a higher education building that has five building area types? 1. School/University 2. Dining: Cafeteria/Fast Food 3. Office 4. Police/
Ventilation (G3.1.2.6)
NC-2009 EAp2:Minimum Energy Performanceposted by Curtis Clark on
A proposed building is designed which the minimum flow rate on the VAV box is the minimum outside air ventilation rate.
Blower door test for 1 in 7 of each room model
NC-2009 IEQp2:Environmental Tobacco Smoke (ETS) Controlposted by Nadia Ayala on
Hi, I was wondering if the v2.2 option (HERS methodology) would still apply for v2009 in regards to the blower door test and number of units that must be tested.
Commissioning
CS-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Karina Hanyzewski on
In a situation where the building undergoes tenant improvements before the shell construction is complete, does the commissioning work need to be adjusted to pick up the changes, even if they are t
Calculating secure bicycle spaces and showers facilities
CS-2009 SSc4.2:Alternative Transportation—Bicycle Storage and Changing Roomsposted by MKK LEED on
Good Morning, I’m calculating the number of spaces for bicycles and showers facilities for C&S project > 300.000 sf.
Alternative-fuel fueling stations for everyone?
NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehiclesposted by Jan Hesse on
We are working on a project with 350 parking spaces and several tenants. One tenant will install 11 alternative-fuel fueling stations (>3% of all parking spaces in the building).
Sewage Conveyance from the site
CI-2009 PIf2:Project Summary Detailsposted by Lakshmikanth Kousik Toppe Jeyabalan on
My project is in Singapore and it is a norm here that all the building sewage will be connected to the public utility drains and send for treatment, reclamation & disposal. I have been requeste
feedback comment
Pilot-Credits WEpc10:Sustainable wastewater managementposted by Mónika Egyed on
In our project, the pilot credit was achievable by 50% reduction from WC and urinal water use.
Concerning Carpet
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Omar Elrawy on
Dear all, We have a project where we intend to pursue Option 1 Path 1, We will install furniture after completing the flush-out, but the architect is concerned about the carpet install
VLT x WFR calculation exceeds 0.18
EBOM-2009 IEQc2.4:Daylight and Viewsposted by Indoor Environmental Quality Team LEED Community Project on
I am reviewing Option 1 Path 2 (Prescriptive) for a visitor's center project. There are several private offices where the VLT x WFR value exceeds the 0.18 threshold.