Task Lighting Required at Copy and Fax Machines
posted by Hernando Miranda on
In December of 2010 a LEED project that was certified as Gold was denied the Lighting Controls credit because task lighting was not provided at copy and fax machines.
No new parking?
NC-2009 SSc4.4:Alternative Transportation—Parking Capacityposted by Lawrence Lile on
We have a "zero lot line" LEED project, where the LEED project boundary is essentially the same as the footprint of the building. There is no new parking provided within the LEED boundary.
Wet/Dry Vacuums - What Product Category
EBOM-2009 IEQc3.4:Green Cleaning—Sustainable Cleaning Equipmentposted by Kelly Witosky on
I am hoping for some guidance on what product category wet/dry vacuums fall into.
EAc1 Design Review Question - Seeking Guidance ASAP
NC-2009 EAc1:Optimize Energy Performanceposted by Joshua Bloom on
If I submit EAc1 in my design review and it gets sent back as likely approved, can I still have the ability to change some things before I submit again for Construction Review?
Renewable Energy and Green Power
NC-2009 EAc1:Optimize Energy Performanceposted by Joshua Bloom on
In EAc1 Related Credits (pg. 260 of BD&C Book) it says that you can mitigate energy use impacts by using renewable energy: refer to EAC2, and EAC6.
Bio-based building materials - foam for use under concrete
NC-2009 MRc6:Rapidly Renewable Materialsposted by Charles Fritzemeier on
I have a project for which we are pursuing Platinum and have an opportunity to use a bio-based material (12"+/-) as a filler under pan deck and concrete.
Baseline Percent against what?
EBOM-2009 WEp1:Minimum Indoor Plumbing Fixture and Fitting Efficiencyposted by Rory Cousino on
Please excuse my ignorance on this, but when determining the baseline to compare, I understand that it depends on the substantial completion date of the plumbing system and if before 1993, then use
Under Construction
NC-2009 SSc2:Development Density and Community Connectivityposted by Lawrence Lile on
I am on a block with two other project under construction at the same time. Can I count the other projects in my calculation of development density?
NC v2009 EAc6 and ID credit
NC-2009 EAc6:Green powerposted by Sheryl Swartzle on
The owner purchase 99% green power in error (70% was to be purchased).
LEED EB:OM SS c 4: No Transport Survey
EBOM-2009 SSc4:Alternative Commuting Transportationposted by Srimannarayana NCVK on
Hi All, We are working for a facility wherein the occupants commute by company buses everyday. Approximately 95% of the occupants use company buspools.