Sub-metering Required?
NC-2009 EAc5:Measurement and Verificationposted by Dave Hubka on
Hello,
We typically implement Option D of IPMVP and calibrate the model once one-year of actual energy data is obtained.
Humidity control - "Unmet humidity load hours"
NC-2009 EAp2:Minimum Energy Performanceposted by Luis Andrade on
Hi all,
I've been reading some of the previous comments about the humidity controls (both humidification and dehumidification). Am I correct to assume:
Equipment efficiencies / DX Cooling Coil EER and COP
NC-2009 EAp2:Minimum Energy Performanceposted by F S on
Hi all.
Question about ASHRAE 90.1 Baseline equipment efficiencies.Project is using System 5 with a Load of around 400kBtu/h. Table 6.8.1A shows the minimum efficiency to be 9.8
CO2 monitor in a booth
CI-2009 IEQc1:Outdoor Air Delivery Monitoringposted by Alicja Bieszyńska on
Hello!
Future tenant space & outside air calculations
CS-2009 IEQp1:Minimum IAQ Performanceposted by Gail Vittori on
The project we are working on has a ground floor tenant space that has the potential to be a restaurant, cafe, small grocer, or even non-food retail (though this last one is relatively unlikely
The parking is Under the building
NC-v4 SSc5:Heat island reductionposted by Radwa Amin on
Hi, Our project is having the parking in the basement floors, makes it all covered. My question is about the parking roof; in our case the roof shall be the "ground floor" and won't be able to co
Habitat for endangered/threatened species
NC-2009 SSc1:Site Selectionposted by Ashley Hu on
Hello there,
I have two project sites in question.
1) An very urban site that was previously a parking lot
Low flow aerators to account for reductions instead of metering
NC-v4 WEp2:Indoor water use reductionposted by S. Sachs on
Has anyone worked with low flow aerators instead of metering since metering is no longer allowed for v4?
What % difference to reference is acceptable?
NC-v4 SSc2:Site development - protect or restore habitatposted by Leanne Conrad on
We are pursuing the chemical testing path for imported soils. My question is what is the acceptable range or percent difference between the reference and imported soils?