Topic | Recent |
---|---|
Collaborative space within pods of workstationsNC-2009 IEQc6.1: Controllability of systems - lightingposted by Joyce Kelly on Jan 30, 2014, 12:09 pm
In the center of a pod of 8 workstations there are two breakout tables for collaborative work. Each workstation has a tasklight. Do the collaborative tables need ambient light level options or... Last reply: Lauren Sparandara, Feb 6, 2014, 4:04 am |
|
Warehouse Lighting-- AgainNC-2009 IEQc6.1: Controllability of systems - lightingposted by Steve Samenski on Oct 17, 2013, 12:25 pm
I've reviewed the threads on here and I see that warehouse lighting is discussed frequently. My understanding is that active warehouse aisles are considered multi-occupant spaces under the credit... Last reply: Peter Dishno, Dec 13, 2013, 5:52 pm |
|
Automatic controls required?NC-2009 IEQc6.1: Controllability of systems - lightingposted by Nicole Kimoto on Nov 8, 2013, 5:18 pm
I have a project that has a shop areas where building occupants will be working. It is very important that the light not turn off automatically when they are working. Can this credit be achieved... Last reply: Lauren Sparandara, Nov 8, 2013, 6:12 pm |
|
IEQ Credit 6.1NC-2009 IEQc6.1: Controllability of systems - lightingposted by Rezkar Abdulmajeed on Nov 4, 2013, 7:58 am
Hi, Can someone guide me please: I am pursuing Credit IEQ 6.1 Light Controls and would like to know if the ASHRAE 2007 standard as mentioned in the LEED requirement to be followed or the... Last reply: Lauren Sparandara, Nov 4, 2013, 10:58 am |
|
Adjunct Professors RoomNC-2009 IEQc6.1: Controllability of systems - lightingposted by Saju Varghese on Oct 31, 2013, 8:27 am
Hi, In one of our project we have a room designated for 6 adjunct professors to work/study/rest. They are not going to stay there for long periods of time, but only when they don't have... Last reply: Kathryn West, Oct 31, 2013, 12:47 pm |
|
Conference Tables in an Open-plan OfficeNC-2009 IEQc6.1: Controllability of systems - lightingposted by Ting Wang on Oct 16, 2013, 9:47 pm
Our project interior has two conference tables placed in an open-plan office, for team discussions and brain-storms that are casual and spontaneous. There is no task lighting or multi-level... Last reply: Ting Wang, Oct 24, 2013, 9:45 pm |
|
On/Off Switch in Locker RoomsNC-2009 IEQc6.1: Controllability of systems - lightingposted by Charline SEYTIER on Sep 24, 2013, 11:49 am
Our design is composed of occupancy sensors in large Locker rooms of a manufacturing plant but they apparently may not be enough to comply with the credit requirements. We suggested to the... Last reply: Lauren Sparandara, Oct 3, 2013, 7:10 pm |
|
Chemical LabsNC-2009 IEQc6.1: Controllability of systems - lightingposted by Saju Varghese on Aug 22, 2013, 10:21 am
Do chemical labs need to comply with this credit? Last reply: Saju Varghese, Oct 3, 2013, 11:25 am |
|
Matching IEQ c6.1 w/ IEQ c6.2NC-2009 IEQc6.1: Controllability of systems - lightingposted by Carrie Laurendine on Sep 20, 2013, 9:31 am
Im documenting these credits for an apartment/condo building. I understand that typically, the space on the form that shows the "total number of individual workspaces in project" must be teh... Last reply: Larissa Oaks, Sep 23, 2013, 11:45 am |
|
Task Lighting in an Open Office AreaNC-2009 IEQc6.1: Controllability of systems - lightingposted by Craig Wery on Sep 11, 2013, 9:26 am
I am try to see what modifications our team can make to comply with the IEQc6.1 Controllability of systems lighting LEED credit. Right now we are short individual lighting controls in our open... Last reply: Lauren Sparandara, Sep 18, 2013, 1:51 pm |