Forum » NC-2009 IEQc3.2
Topic

Permanent furniture

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Pascal Genest-Richard on Jul 4, 2014, 5:22 pm

We would like to know if it is possible to start the flush out (and maybe even finish it) before all permanent furniture is installed. The furniture is fabricated in a shop outside the site and...

Last reply: Tristan Roberts, Jul 26, 2014, 8:32 am

Concerning Carpet

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Omar Elrawy on Jun 26, 2014, 5:30 am

Dear all,
We have a project where we intend to pursue Option 1 Path 1, We will install furniture after completing the flush-out, but the architect is concerned about the carpet...

Last reply: Haytham Mohamed, Jul 3, 2014, 4:08 am

Expansion project FLUSH OUT

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Jorge Torres-Coto on Jun 13, 2014, 5:35 pm

We have a project that is an expansion to an existing facility. It is NOT an addition. Though the majority of the existing facility was unrenovated, with the exception of one ventilation system...

Floor Area for Flush Out

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Nikhilesh Srinivasan on May 20, 2014, 1:51 pm

I'm looking for some help with the area to be used for a flush out calculation. The gross project area included in PI-Form 3 includes electric/janitor closets, core toilets, mechanical room and...

Performing testing under Option 2- number of samples

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Adriana Hansen on May 19, 2014, 5:13 pm

For performing testing under Option 2 (...

Last reply: Tom Nichols, May 20, 2014, 12:44 pm

IBC Occupancy Classification & Testing Requirements

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Zach Hoffman on May 16, 2014, 8:09 pm

I am wondering if IBC Group S-1 Occupancy zones are required to be tested per IEQc3.2.
On this project (vehicle maintenance facility), the specific zones within the S-1 classification are...

Last reply: Dale Walsh, May 16, 2014, 11:42 pm

IAQ Testing- Maximum Concentrations

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Donald Green on Feb 3, 2014, 10:06 am

to the v4 question, please do it over on the v4 forum. Thanks! Log in or register to post comments ...

Last reply: Tristan Roberts, May 5, 2014, 3:49 pm

Flush Out Path 1 Only During Daytime

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Esteban Martinez on Apr 29, 2014, 6:34 pm

We are currently pursuing this credit using the flush out option Path 1. We are capable of maintaining the temperature in at least 60°F and RH no higher than 60% since the ventilation systems are...

IEQc3.2 Option 2: Air Testing

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Christopher Strunk on Apr 29, 2014, 2:27 pm

Currently doing a LEED v.2009 project and are looking to pursue IEQc3.2, Option 2. We got a question from the air quality tester asking about the specific requirements for testing. The testing...

Last reply: Christopher Strunk, Apr 29, 2014, 3:11 pm

Do all units have to run at 100% OA for this credit?

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Saju Varghese on Apr 17, 2014, 3:14 pm

We have 4 A/C Units providing air conditioning to a building, two of them are 100% OA units and two of them are providing the total air supply cfm (OA + recirulated air) is 7000 cfm and 8600...

Last reply: Saju Varghese, Apr 21, 2014, 5:40 pm