Option 1 with no dedicated smoking areas

NC-2009 IEQp2: Environmental Tobacco Smoke (ETS) Control
posted by Annalise Reichert on Jan 13, 2014, 4:52 pm

I am working on a project that has installed signage near major entrances that prohibits smoking within 25 feet of all doors and windows. However, designated smoking areas beyond the 25 foot...

Last reply: Tristan Roberts, Jan 13, 2014, 4:55 pm

Filter on Zone's Exhaust

NC-2009 IEQp2: Environmental Tobacco Smoke (ETS) Control
posted by Omar Elrawy on Dec 2, 2013, 5:07 am

I need to know if I should place filter on the smoking zones' exhaust duct?
If yes, should it be HEPA filter as it is placed on the schematic diagram in the reference guide?

Thanks...

Last reply: Ben Stanley, Dec 30, 2013, 5:40 pm

ANSI/ASTM-E779-03 vs E779-10

NC-2009 IEQp2: Environmental Tobacco Smoke (ETS) Control
posted by María Fernanda Aguirre on Dec 3, 2013, 2:48 pm

For Mid-rise residential buildings it is required to perform a blower door test according E779-03 but international...

Last reply: Ben Stanley, Dec 30, 2013, 5:27 pm

Signatory Statement and Signage

NC-2009 IEQp2: Environmental Tobacco Smoke (ETS) Control
posted by Daniel Garavito on Aug 9, 2013, 2:54 pm

We are currently working in a project located in New York City. The owner owns the entire floor where the project is located. Because of thet I have a couple of questioss:

1- As what...

Last reply: Tristan Roberts, Nov 3, 2013, 7:50 pm

Timing of blower door tests

NC-2009 IEQp2: Environmental Tobacco Smoke (ETS) Control
posted by Ilana Judah on Sep 11, 2013, 1:25 pm

When can the blower door test take place? Can it be done when the drywall has been completed or do the cabinetry and appliances need to be installed as well?

Last reply: Tristan Roberts, Nov 3, 2013, 7:48 pm

enlosed smoking room outside the building

NC-2009 IEQp2: Environmental Tobacco Smoke (ETS) Control
posted by Erin Holdenried on Apr 16, 2013, 3:13 pm

Hello, I have a project that does not allow smoking within the building. However, there are small one room kiosks outside the building that allow smoking. These small structures are more than...

Last reply: Tristan Roberts, Nov 3, 2013, 7:43 pm

Smoking Prohibition in a Border Crossing Building

NC-2009 IEQp2: Environmental Tobacco Smoke (ETS) Control
posted by María Fernanda Aguirre on Apr 19, 2013, 9:26 am

We are assessing the possibility of pursuing LEED Certification for a Complex of four buildings at the Border Crossing between Chile and Argentina. One of these buildings is residential and will...

Last reply: Tristan Roberts, Nov 3, 2013, 7:40 pm

smoking is allowed in hotel guest rooms

NC-2009 IEQp2: Environmental Tobacco Smoke (ETS) Control
posted by Noriko Nagazumi on May 14, 2013, 8:53 pm

Hi,
Our project is mixed use commercial office building including hotel. There are about 100 guest rooms on hotel floors, and smoking is permitted in 30% of these rooms. Is it acceptable to...

Last reply: Tristan Roberts, Nov 3, 2013, 7:38 pm

Alternative Test Method for Blower Door Test.

NC-2009 IEQp2: Environmental Tobacco Smoke (ETS) Control
posted by Haytham Mohamed on Sep 16, 2013, 9:13 am

We have a medium high-rise residential tower on Abu Dhabi, 4 apartments each floor, the return and supply for each flat are not connected with each others, the fire damper is located above the...

Last reply: Haytham Mohamed, Oct 10, 2013, 3:10 am

How can I provide blower door test results before occupancy?

NC-2009 IEQp2: Environmental Tobacco Smoke (ETS) Control
posted by adi ashkenazi on Jul 7, 2013, 10:26 am

Hi,
On the credit form I must upload blower door test results but this credit is a design phase credit and the test is only after construction is complete. Can someone share how they solved...

Last reply: Peter Doo, Sep 27, 2013, 4:58 pm