posted by Francesco Passerini on Apr 6, 2012, 2:01 pm

Hello.

I’m dealing with the calculation method for the credits relative to EA section.

I don’t understand the meaning of the following sentence of paragraph G2.4 of ANSI/ASHRAE/...

Last reply: Marcus Sheffer, Apr 6, 2012, 2:32 pm

90.1- Air-side Economizer & Humidity Requirements

NC-2009 EAp2: Minimum Energy Performance
posted by Charles Daze on Mar 30, 2012, 4:12 pm

I have a 90.1 App G. interpretation question.

G3.1.2.6 requires economizers in certain climates. The only exceptions are for gas-phase air cleaning and supermarket open refrigerated...

Last reply: Marcus Sheffer, Apr 3, 2012, 10:17 am

EAp2-7 Example Spreadsheet

NC-2009 EAp2: Minimum Energy Performance
posted by AAME User on Apr 2, 2012, 7:32 pm

Can anyone point me towards an EAp2-7 example spreadsheet filled out complete for reference? The spreadsheet required by LEEDonline is a little "vague" regarding what it wants for some of the...

Baseline PTAC sizing

NC-2009 EAp2: Minimum Energy Performance
posted by April Ambrose on Mar 27, 2012, 12:13 pm

I have a residential facility seeking LEED v2009 certification with small room loads (approx 2,000 BTU/hr).

My understanding of ASHRAE 90.1-2007 is that these spaces need to be modeled...

Last reply: Marcus Sheffer, Mar 27, 2012, 1:11 pm

Energy Standards Comparison

NC-2009 EAp2: Minimum Energy Performance
posted by Sam Watters on Mar 26, 2012, 12:05 pm

Hello,

I'm trying to work through how much more efficient my project will be over ASHRAE 90.1 2007, and I wondered if anyone had experience with how the standard compares to IEC 2006....

Last reply: Sam Watters , Mar 27, 2012, 12:24 pm

Window to wall ratio

NC-2009 EAp2: Minimum Energy Performance
posted by Katherine Ann Resurreccion on Mar 23, 2012, 3:52 am

I’m working on project with two mid-rise buildings, one for the office and the other is for parking garage mostly are naturally ventilated. There are small driver’s lounges in the garage building...

Last reply: Marcus Sheffer, Mar 23, 2012, 8:53 am

Lighting Power Allowance

NC-2009 EAp2: Minimum Energy Performance
posted by David Weigel, PE on Mar 21, 2012, 3:28 pm

I am working on a new facility that is mixed-use health care, research laboratory, and conference center.

Computing lighting power...

Last reply: Marcus Sheffer, Mar 21, 2012, 4:52 pm

Building Type Method or Space-by-Space on Construction phase

NC-2009 EAp2: Minimum Energy Performance
posted by Katherine Ann Resurreccion on Mar 15, 2012, 9:34 pm

If same Lighting Power Density (W/sf) was used in all zones during the design phase using Building Type Method, should we switch to space by space on its final stage?

Appendix-G says it...

Last reply: Marcus Sheffer, Mar 16, 2012, 9:58 am

Mandatory Provitions- Fenestration and Doors

NC-2009 EAp2: Minimum Energy Performance
posted by Paula Hernandez on Mar 15, 2012, 2:58 pm

Hi,

I have an air conditioned warehouse, where wine will be sotored, and it has two doors, with now vestibules.
these doors will be used aproximatly once a week for loading and...

Last reply: Marcus Sheffer, Mar 15, 2012, 4:52 pm

Exceptional Calculation for Elevator

NC-2009 EAp2: Minimum Energy Performance
posted by Thomas Hellmann on Mar 14, 2012, 11:02 am

My read on ASHRAE-90.1 and numerous forums, is that USGBC may allow for an exceptional calculation to be performed for elevator energy savings, provided that;
1) Schedule of operation...

Last reply: Marcus Sheffer, Mar 14, 2012, 11:56 am