Log in
Forum » Warehouses-NC-v4 EQc7
Topic

upload daylight calculation of seperate building in a Group for a Master Site

Warehouses-NC-v4 EQc7: Daylight
posted by N. Josef Nassif on Apr 26, 2023, 7:39 am

Dear Community 

I hope you are doing fine. 

We are doing a master site (office + Warehouse building + Techology Building) project where the two building (warehouse and technology)...

Refrigerated Areas

Warehouses-NC-v4 EQc7: Daylight
posted by Ricardo Sá on Jun 12, 2019, 6:11 am

Dear All,

we are evaluating the possibility of certifying a distribution center with large refrigerated areas. These areas are regularly occupied.