To use Energy star portfolio manager

Data-Centers-EBOM-v4 EAp2: Minimum Energy Performance
posted by Milan Kumawat on Jan 7, 2022, 8:33 am

We are trying to fill the energy star for data center. If we create a single meter for whole building electricity consumption then our score is not reflecting on energy star portal. If we are...

Data Center in Portfolio Manager

Data-Centers-EBOM-v4 EAp2: Minimum Energy Performance
posted by Charalampos Giannikopoulos on Nov 13, 2014, 12:03 pm

How should a Data Center building facility be included in the Portfolio Manager? The building hosts the data center and the supporting offices. In particular, 60% of its GFA is allocated to pure...

Last reply: Trista Brown, Aug 28, 2017, 2:19 pm