shgc Values

NC-2009 EAc1:Optimize energy performance
posted by  TOMAS URIBE  on 

Hello Marcus. The fenestration supplier of a project gave us SHGC values from a simulation. We would like to know if it is acceptable for LEED simulation.

1
Wed Feb 12, 2014, 8:02 pm

CitiBike- Bicycle Commuting SS c4-3

NC-2009 SSc4.2:Alternative transportation - bicycle storage and changing rooms
posted by  Alfred Servodidio  on 

Our project in NYC has a Citi Bike location less than 200 yards from the entrance. The owner will pay for up to 80% of the annual cost for all employees.

1
Wed Feb 12, 2014, 8:34 pm

Building Demolition

NC-2009 MRc1.1:Building reuse - maintain existing walls, floors and roof
posted by  Chris Eger  on 

We are demolishing a large building that is no longer in use and is twice the size of an existing portion being retained.

1
Fri Mar 7, 2014, 5:22 pm

Using the calculator (continued)

EBOM-2009 IEQp1:Minimum indoor air quality performance
posted by  Christina Reeves  on 

Hello again, We now have the 62MZ spreadsheet working (thanks again!), but a few more questions have come up as our ME works through it. Can anyone provide some insight on these? 1.

1
Thu Feb 13, 2014, 6:02 pm

Tenant Metering Questions

CS-2009 EAc5.2:Measurement and verification - tenant submetering
posted by  Marina Andrade  on 

Hi, I'm working on a project that has many storage modules that will be occupied by tenants.

1
Thu Feb 13, 2014, 4:05 pm

Rebar - Offsite Scrap Recycling

CS-2009 MRc2:Construction waste management
posted by  Roberto Meza  on 

Hello, We have an interesting situation at a large project, Rebar is being bought from a company which at the same time offers to bend it into the various figures needed for columns etc.

1
Mon Feb 17, 2014, 5:26 pm

EAp2 form issue on table 2-6

CS-2009 EAp2:Minimum energy performance
posted by  charles bell  on 

Our project is a CS mixed use: hopefully this is not too general a question. We cannot get the table EAp2-6 to pull down results from the previous tables.

1
Mon Feb 17, 2014, 4:38 pm

Cold, dark warehouse, round 3 (at least)

CS-2009 MRp1:Storage and collection of recyclables
posted by  Tiffany Moore  on 

I just received review comments back on MRp1 that I simply can't validate. I'd appreciate any help or advice that might be out there.

1
Thu Feb 13, 2014, 11:41 pm

Pool

NC-2009 SSc5.2:Site development - maximize open space
posted by  Jorge Lopez de Obeso  on 

If SSc2 is achieved, would a swimming pool count towards credit achievement? I´d think so, however I read other posts and there is a comment that says no... Does anyone have a positive feedback a

1
Fri Feb 14, 2014, 1:42 am

temporized faucet

NC-2009 WEp1:Water use reduction
posted by  LEEDme Lorenzi  on 

The water use reduction additional guidance says: the flow rate is determined using the flow rate in gallons per minute (gpm) and the duration setting (in seconds) for the metering faucet.

1
Fri Feb 14, 2014, 12:45 pm