Solar Panels outside LEED project boundary

NC-2009 EAc1:Optimize energy performance
posted by  Kalyan Nishtala  on 

Hi, I am currently working on a LEED project which will pursue renewable energy credit and also count the savings towards EAc1 points.

1
Mon Aug 26, 2013, 7:41 pm

M&V Template - End Use Metering Table

NC-2009 EAc5:Measurement and verification
posted by  Candice Rogers  on 

Hello - We're submitting for M&V under LEEDv2009. We're going with Option D - Calibrated Simulation. Our energy model did not use the performance path.

1
Mon Aug 26, 2013, 9:49 pm

LeedOnLine Forms Incorrect

CS-2009 EAp2:Minimum energy performance
posted by  Thomas Newbold  on 

I am having a problem with LeedOnLine and USGBC hasn't been any help.

1
Mon Aug 26, 2013, 10:21 pm

SEED evaluator tool

ND-v2009 NPDc12:Community outreach and involvement
posted by  USGBC Colorado  on 

Are you aware of project teams using the SEED (social, economic, environmental design) evaluator tool http://www.seednetwork.org/ as a strategy to achieve this credit?

1
Mon Aug 26, 2013, 11:36 pm

Contractual Relationship

CI-2009 EAc2:Enhanced commissioning
posted by  Brian Smith  on 

The owner is looking for CI-2009 Enhanced Cx on a project. The CxA was originally contracted through the GC as they were not a prequalified vendor of the Owner.

1
Fri Sep 6, 2013, 9:47 pm

Documentation for upload

NC-2009 SSc1:Site selection
posted by  Olga Kozub  on 

I have a project in Russia. In Russia we use the local equivalent of the United States Code of Federal Regulations named State Immovable Property Cadastre.

1
Sun Nov 3, 2013, 3:35 am

Materials to be included

CS-2009 MRp1:Storage and collection of recyclables
posted by  Michael Haugeneder  on 

We are working on a project in Berlin.

1
Mon Nov 4, 2013, 6:08 pm

Accessible Bus Stop

NC-2009 SSc4.1:Alternative transportation - public transportation access
posted by  Brett Beckemeyer  on 

Our project has several bus stops within the 1/4 mile radius, and what I would consider to be the most direct route along the street to the stops is also within 1/4 mile walking distance.

1
Sun Nov 3, 2013, 3:03 am

Rating System selection for an Existing Retail building

LEED Rating System Selection
posted by  Therese Malm  on 

We have a building which is an existing retail & manifacturing building. Which rating system is the most appropriate for seeking certification: EBOM or CI Retail?

1
Tue Aug 27, 2013, 5:50 pm

Green roof deck

NC-2009 SSc6.1:Stormwater design - quantity control
posted by  mariela garate  on 

Hi, We are willing to use an innovative type of green roof that's based on compacted plastic waste board and textile (1,3cms thickness + textile). This substrate replaces the need of soil.