Forum quick links
Building Envelope Air infiltration
CS-v4 EAp2:Minimum energy performanceposted by Patrice McVeigh on
Hi All, I am trying to establish if a project can take benefit in the energy model for an improved air infiltration rate for the building envelope over the baseline model.
Building Level Water Metering
EBOM-v4 WEp2:Building-level water meteringposted by sebastian castañeda on
I have a doubt, we have a project of a complex of 3 buildings that is located inside a University Campus.
Diverse Uses within a Shopping Center
CS-v4 LTc4:Surrounding density and diverse usesposted by Frank Sherman on
The planned C+S development is a shopping center that will include retail, restaurants, a grocery store and movie theater.
New to LEED Submitals
posted by Joel Clonch on
I have a mill-work submittal that requests : LEED Submittals: 1. Product Data showing VOC content does not exceed 30 g/L for wood adhesives and 80 g/L for contact adhesives. 2.
Solar panels serving another building
EBOM-2009 SSc7.2:Heat Island Reduction—Roofposted by Rasita Masalskyte on
If solar panels on our building‘s roof are serving another building‘s energy needs, can we still exclude these solar panels from calculations as mechanical equipment?
Decorative Lighting (Options B & C)
CI-2009 EAc1.2:Optimize Energy Performance—Lighting Controlsposted by Ciaran McCabe on
Should decorative lighting be included to Options B&C ? This decorative lighting is not within 15ft of windows and is independently controlled by occupancy sensors.
IN: Green Building Education
EBOM-v4 INc1:Innovationposted by Alexa Stone on
One of the elements of this credit includes: The development of a manual, guideline or case study to inform the design of other buildings based on the successes of this project.
Trace 700 Performance Summary Report
NC-2009 EAp2:Minimum Energy Performanceposted by Aru Sau on
Is the Performance Summary Report generated by Trane Trace 700 (Ver 3.0) be enough for the LEED V4 EA credit?
Non-default Historical Occupancy Rate for Hotel Project
posted by Annalise Reichert on
I am working on a hotel project that has historical occupancy rates of 80%, which is higher than the LEED default rate of 60%.
Alternative Outdoor Air Supply for Basement Parking
CS-2009 IEQp1:Minimum IAQ Performanceposted by Katherine Ann Resurreccion on
Hi All, We would like to get your opinion in the situation below if approach is acceptable to IEQp1: We have an enclosed Driver’s lounge, Lift lobbies and Administration office at the Basement fl