V4 - SSc5 - Heat Island Reduction - occupiable roofs
CS-v4 SSc5:Heat island reductionposted by Thomas Gibbons on
Hi folks,
SSc5 - Heat Island Reduction
Core & Shell V4
Central Plants and LEEDv4 Enhanced IAQ Management Strategies
posted by Allison Wilson on
Hey there hive mind,
getting hot water from CHP, but not the power. Can I still get the credit of the power produced?
NC-v4 EAp2:Minimum energy performanceposted by Moses Chong on
Hi! My project is getting hot water from the central combined heat and power plant in the campus, but it's NOT getting the electricity from it.
Definition of "Functional Entry"
NC-v4 LTc6:Bicycle facilitiesposted by Marion THIBAULT on
Dear all LEED user,
Project with NO off-set parking
CI-v4.1 LTc5:Reduced Parking Footprintposted by Joel Serrat on
Good afternoon,
LEED 4.1 Tier 2 & 3 Renewable Energy and District or Campus Thermal Energy (DES)
NC-v4.1 EAc5:Renewable Energyposted by Hans Marsman on
We are working on a building connected to a campus central plant (DES).
MEPC input - Total cooling & heating capacity
CS-v4 EAc2:Optimize energy performanceposted by Lenka Matějíčková on
Hi to All,
I would like to clarify the MEPC calculator inputs for LEEDv4 under C&S.
In the Air-Side HVAC tab:
1/ Cooling & heating capacities:
Modeling baseline DES under Option 1, Path 2 - full DES performance accounting
CS-v4 EAc2:Optimize energy performanceposted by Lenka Matějíčková on
Hi All,
We are modeling an industrial plant including the plant DES system, pursuing the Option 1, Path 2. Full DES Performance Accounting.
PV panels on Roof
CS-v4 SSc5:Heat island reductionposted by Andrea Tirao on