2 buildings - one certification

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  Henrique Mendes  on 

Hello all! We are working on a project that will be two buildings, used for warehouses. The buildings are really close to each other and will share some systems and structures, such as the parking

3
Mr.
Green Domus | Desenvolvimento Sustentável
LEEDuser Basic Member
13 thumbs up
Tue Apr 22, 2014, 8:38 pm

Daylight analysis - inter-reflection

NC-2009 IEQc8.1:Daylight and Views—Daylight
posted by  Luana Bertoletti  on 

Hi, I have a doubt related to the considerations that should be assumed in order to perform the daylight analysis simulation.

8
Tue Apr 22, 2014, 8:13 pm

Potable water backup

NC-2009 WEc1:Water Efficient Landscaping
posted by  Heather Holdridge  on 

Can a project still earn 4 points under option 2 if a cistern has potable water backup? Could we demonstrate that it wouldn't be used through the path 1 calculations?

4
Tue Apr 22, 2014, 6:54 pm
17
Tue Apr 22, 2014, 11:50 am

Do all units have to run at 100% OA for this credit?

NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Saju Varghese  on 

We have 4 A/C Units providing air conditioning to a building, two of them are 100% OA units and two of them are providing the total air supply cfm (OA + recirulated air) is 7000 cfm and 8600 respec

4
Mon Apr 21, 2014, 9:40 pm

LEED ND _Exam

General forums
posted by  Lakshmi Nair  on 

Hi Tristan , I am presently a LEED AP ( BD+C ). I was hoping to write LEED ND and become a LEED AP ( ND ). Should this be also done before June 15th ?

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Mon Apr 21, 2014, 11:14 am

RH control with dew point control logic for IEQ 6.2

NC-2009 IEQc6.2:Controllability of Systems—Thermal Comfort
posted by  J I  on 

This project is based in highly humid place, we have used dew point control logic for AHU control. In this control logic, we are controlling 2-way chilled water valve from signal from supply air

3
Default Avatar
President
Weatherby Design & Co. Engineers
LEEDuser Basic Member
67 thumbs up
Mon Apr 21, 2014, 10:45 am

Control Via Software Platform

NC-2009 IEQc6.1:Controllability of Systems—Lighting
posted by  Andrew Gil  on 

Hello All, An unfortunate error was made when “multi-occupant space” was assumed by a team member to include a shared office space, and construction is complete.

2
LEED AP BD+C, O+M, Green Globes Professional
JLL
LEEDuser Basic Member
112 thumbs up
Fri Apr 18, 2014, 2:22 pm

HVAC system changed after certification completed

General forums
posted by  Johannes Hopf  on 

Our project (LEED NC 2009 Gold) was certified 3 years ago. Now the new landlord would like to add humidification to AHU. Is the certification affected?

3
Thu Apr 17, 2014, 10:57 pm

Elevators (Lift/Escalators) & LEED EAC1 credit

Schools-2009 EAc1:Optimize Energy Performance
posted by  Ameet AA  on 

Can I include the Elevators (Lift/Escalators) in EAC1 credit calculation using the whole building simulation method? I was told by an Elevator supplier that Regenerative Converter in lift could be

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Wed Apr 16, 2014, 8:11 pm