MR credits- Option 1 & Option 2CS-v4 MRc4: Building product disclosure and optimization - material ingredientsposted by Yoyo Shek on May 20, 2019, 6:19 am
Hello all, We are currently working on a C&S project (v.4). As the requirements for option 2 is an enhancement of option 1, it is possible to source a product that fulfills option 2... |
|
Option 2- threshold of 30% of the costs attributed Structure and EnclosureCS-v4 MRc4: Building product disclosure and optimization - material ingredientsposted by Barry Farren on Nov 14, 2018, 6:48 am
For Option 2, demonstrating that 25% of the cost of the project materials meet REACh compliance, There is a requirement that only 30% of these material costs can be attributed to the... |
|
Option 3 Guidance Now Available!CS-v4 MRc4: Building product disclosure and optimization - material ingredientsposted by Paula Melton on Dec 28, 2015, 10:03 am